Fukushima Daiichi NPS Prompt Report

2013

Status of TEPCO's Nuclear Power Stations after the Tohoku-Chihou-Taiheiyou-Oki Earthquake

Aug 31, 2013 Water Leak at a Tank in the H4 area in Fukushima Daiichi Nuclear Power Station (Follow-up Information 19)
Aug 31, 2013 Water Leak at a Tank in the H4 area in Fukushima Daiichi Nuclear Power Station (Follow-up Information 18)
Aug 31, 2013 Physical Disorder of a Worker at Fukushima Daiichi Nuclear Power Station
Aug 31, 2013 Water Leak at a Tank in the H4 area in Fukushima Daiichi Nuclear Power Station (Follow-up Information 17)
Aug 30, 2013 Tritium Density Result of Water Quality Survey inside the Port of Fukushima Daiichi NPS (Follow-up Information 45)
Aug 30, 2013 Water Leak at a Tank in the H4 area in Fukushima Daiichi Nuclear Power Station (Follow-up Information 16)
Aug 30, 2013 Tritium Density Result of Water Quality Survey inside the Port of Fukushima Daiichi NPS (Follow-up Information 44)
Aug 29, 2013 Water Leak at a Tank in the H4 area in Fukushima Daiichi Nuclear Power Station (Follow-up Information 15)
Aug 29, 2013 Water Leak at a Tank in the H4 area in Fukushima Daiichi Nuclear Power Station (Follow-up Information 14)
Aug 27, 2013 Water Leak at a Tank in the H4 area in Fukushima Daiichi Nuclear Power Station (Follow-up Information 13)
Aug 26, 2013 Announcement on Press Conference Represented by President Hirose (from 6:30 PM on August 26)
Aug 25, 2013 Water Leak at a Tank in the H4 area in Fukushima Daiichi Nuclear Power Station (Follow-up Information 12)
Aug 25, 2013 Water Leak during a Water Filling Work to the Reactor Well of Unit 4
Aug 24, 2013 Pressure Change in Unit 2 Primary Containment Vessel at Fukushima Daiichi NPS
Aug 24, 2013 Tritium Density Result of Water Quality Survey inside the Port of Fukushima Daiichi NPS (Follow-up Information 43)
Aug 24, 2013 Tritium Density Result of Water Quality Survey inside the Port of Fukushima Daiichi NPS (Follow-up Information 42)
Aug 23, 2013 Alarm Went Off at the Dust Monitor Installed in Front of the Main Anti-earthquake Building at Fukushima Daiichi Nuclear Power Station (Follow-up Information 5)
Aug 23, 2013 Tritium Density Result of Water Quality Survey inside the Port of Fukushima Daiichi NPS (Follow-up Information 41)
Aug 23, 2013 Completion of Installation of the Well Point at the East Side of Unit 1, 2 Turbine Building in Fukushima Daiichi Nuclear Power Station
Aug 23, 2013 Water Leak at a Tank in the H4 area in Fukushima Daiichi Nuclear Power Station (Follow-up Information 11)
Aug 22, 2013 Water Leak at a Tank in the H4 area in Fukushima Daiichi Nuclear Power Station (Follow-up Information 10)
Aug 22, 2013 Tritium Density Result of Water Quality Survey inside the Port of Fukushima Daiichi NPS (Follow-up Information 40)
Aug 21, 2013 Tritium Density Result of Water Quality Survey inside the Port of Fukushima Daiichi NPS (Follow-up Information 39)
Aug 21, 2013 Tritium Density Result of Water Quality Survey inside the Port of Fukushima Daiichi NPS (Follow-up Information 38)
Aug 21, 2013 Water Leak at a Tank in the H4 area in Fukushima Daiichi Nuclear Power Station (Follow-up Information 9 and Correction)
Aug 21, 2013 Water Leak at a Tank in the H4 area in Fukushima Daiichi Nuclear Power Station (Follow-up Information 8)
Aug 21, 2013 Water Leak at a Tank in the H4 area in Fukushima Daiichi Nuclear Power Station (Follow-up Information 7)
Aug 21, 2013 Water Leak at a Tank in the H4 area in Fukushima Daiichi Nuclear Power Station (Follow-up Information 6)
Aug 20, 2013 Alarm Went Off at the Dust Monitor Installed in Front of the Main Anti-earthquake Building at Fukushima Daiichi Nuclear Power Station (Follow-up Information 4)
Aug 20, 2013 Water Leak at a Tank in the H4 area in Fukushima Daiichi Nuclear Power Station (Follow-up Information 5)
Aug 20, 2013 Tritium Density Result of Water Quality Survey inside the Port of Fukushima Daiichi NPS (Follow-up Information 37)
Aug 20, 2013 <Revised Version>Water Leak at a Tank in the H4 area in Fukushima Daiichi Nuclear Power Station (Follow-up Information 4)
Aug 19, 2013 Water Leak at a Tank in the H4 area in Fukushima Daiichi Nuclear Power Station (Revision)
Aug 19, 2013 Alarm Went Off at the Dust Monitor Installed in Front of the Main Anti-earthquake Building at Fukushima Daiichi Nuclear Power Station (Follow-up Information 3)
Aug 19, 2013 Water Leak at a Tank in the H4 area in Fukushima Daiichi Nuclear Power Station (Follow-up Information 2)
Aug 19, 2013 Alarm Went Off at the Dust Monitor Installed in Front of the Main Anti-earthquake Building at Fukushima Daiichi Nuclear Power Station (Follow-up Information 2)
Aug 19, 2013 Water Leak at a Tank in the H4 area in Fukushima Daiichi Nuclear Power Station (Follow-up Information)
Aug 19, 2013 Water Leak at a Tank in the H4 area in Fukushima Daiichi Nuclear Power Station
Aug 19, 2013 Alarm Went Off at the Dust Monitor Installed in Front of the Main Anti-earthquake Building at Fukushima Daiichi Nuclear Power Station (Follow-up Information)
Aug 19, 2013 Alarm Went Off at the Dust Monitor Installed in Front of the Main Anti-earthquake Building at Fukushima Daiichi Nuclear Power Station
Aug 18, 2013 Status of Pumping up of Groundwater from the Well Point at the East Side of Unit 1, 2 Turbine Building in Fukushima Daiichi Nuclear Power Station (Follow-up information)
Aug 17, 2013 Water Leak from the Underground Reservoirs in Fukushima Daiichi Nuclear Power Station (Follow-up Information No.216)
Aug 17, 2013 Status of Pumping up of Groundwater from the Well Point at the East Side of Unit 1, 2 Turbine Building in Fukushima Daiichi Nuclear Power Station
Aug 17, 2013 Tritium Density Result of Water Quality Survey inside the Port of Fukushima Daiichi NPS (Follow-up Information 36)
Aug 15, 2013 Commencement of Pumping up of Groundwater from the Well Point at the East Side of Unit 1, 2 Turbine Building in Fukushima Daiichi Nuclear Power Station
Aug 15, 2013 Tritium Density Result of Water Quality Survey inside the Port of Fukushima Daiichi NPS (Follow-up Information 35)
Aug 14, 2013 Alarm Went off at the Dust Monitor Installed in front of the Main Anti-earthquake Building at Fukushima Daiichi Nuclear Power Station (Revision 2)
Aug 12, 2013 Physical Disorder of a Worker at Resting Place of the Registration Center at Fukushima Daiichi Nuclear Power Station
Aug 12, 2013 Alarm Went off at the Dust Monitor Installed in front of the Main Anti-earthquake Building at Fukushima Daiichi Nuclear Power Station (Revision)
Aug 12, 2013 Alarm Went off at the Dust Monitor Installed in front of the Main Anti-earthquake Building at Fukushima Daiichi Nuclear Power Station (Follow-up Information No.3)
Aug 12, 2013 Alarm Went off at the Dust Monitor Installed in front of the Main Anti-earthquake Building at Fukushima Daiichi Nuclear Power Station (Follow-up Information No.2)
Aug 12, 2013 Alarm Went off at the Dust Monitor Installed in front of the Main Anti-earthquake Building at Fukushima Daiichi Nuclear Power Station (Follow-up Information)
Aug 12, 2013 Alarm Went off at the Dust Monitor Installed in front of the Main Anti-earthquake Building at Fukushima Daiichi Nuclear Power Station
Aug 11, 2013 Tritium Density Result of Water Quality Survey inside the Port of Fukushima Daiichi NPS (Follow-up Information 34)
Aug 10, 2013 Alarm Went off at the Second Cesium Adsorption Apparatus (SARRY) at Fukushima Daiichi Nuclear Power Station (Follow-up Information)
Aug 10, 2013 Measurement Results of Water Level of the Groundwater Observation Hole No.1-8 at Fukushima Daiichi Nuclear Power Station
Aug 10, 2013 Alarm Went off at the Second Cesium Adsorption Apparatus (SARRY) at Fukushima Daiichi Nuclear Power Station
Aug 9, 2013 Tritium Density Result of Water Quality Survey inside the Port of Fukushima Daiichi NPS (Follow-up Information 33)
Aug 9, 2013 Status of Pumping up Groundwater from the Water Collection Pit at the East Side of the Unit 1, 2 Turbine Building in Fukushima Daiichi Nuclear Power Station
Aug 9, 2013 Commencement of Pumping up of Groundwater from the Water Collection Pit at the East Side of the Unit 1, 2 Turbine Building in Fukushima Daiichi Nuclear Power Station
Aug 8, 2013 Tritium Density Result of Water Quality Survey inside the Port of Fukushima Daiichi NPS (Follow-up Information 32)
Aug 7, 2013 Tritium Density Result of Water Quality Survey inside the Port of Fukushima Daiichi NPS (Follow-up Information 31)
Aug 7, 2013 Steam Found Near the Central Part of the Fifth Floor (Equipment Storage Pool Side) of Unit 3 Reactor Building at Fukushima Daiichi Nuclear Power Station (Follow-up Information 19)
Aug 6, 2013 Tritium Density Result of Water Quality Survey inside the Port of Fukushima Daiichi NPS (Follow-up Information 30)
Aug 6, 2013 Steam Found Near the Central Part of the Fifth Floor (Equipment Storage Pool Side) of Unit 3 Reactor Building at Fukushima Daiichi Nuclear Power Station (Follow-up Information 18)
Aug 5, 2013 Tritium Density Result of Water Quality Survey inside the Port of Fukushima Daiichi NPS (Follow-up Information 29)
Aug 5, 2013 Fire Alarm Went off at the Third Floor Area of the Auxiliary Operation Shared Facility (Common Pool Building) at Fukushima Daiichi Nuclear Power Station
Aug 5, 2013 Steam Found Near the Central Part of the Fifth Floor (Equipment Storage Pool Side) of Unit 3 Reactor Building at Fukushima Daiichi Nuclear Power Station (Follow-up Information 17)
Aug 5, 2013 Steam Found Near the Central Part of the Fifth Floor (Equipment Storage Pool Side) of Unit 3 Reactor Building at Fukushima Daiichi Nuclear Power Station (Follow-up Information 16)
Aug 4, 2013 Steam Found Near the Central Part of the Fifth Floor (Equipment Storage Pool Side) of Unit 3 Reactor Building at Fukushima Daiichi Nuclear Power Station (Follow-up Information 15)
Aug 2, 2013 Tritium Density Result of Water Quality Survey inside the Port of Fukushima Daiichi NPS (Follow-up Information 28)
Aug 2, 2013 Tritium Density Result of Water Quality Survey inside the Port of Fukushima Daiichi NPS (Follow-up Information 27)
Aug 1, 2013 Tritium Density Result of Water Quality Survey inside the Port of Fukushima Daiichi NPS (Follow-up Information 26)
Aug 1, 2013 Tritium Density Result of Water Quality Survey inside the Port of Fukushima Daiichi NPS (Follow-up Information 25)