Daily measurement data and analysis results are announced, enabling the public including local communities to confirm radiation levels in the area.
Use of the data is explained here.

Results of radioactive material analysis at each collection point (for October 2023)

Air

Air at power station site

Radionuclide analysis is conducted of air collected inside the power station site.

Note:As of the samples collected August 30, 2017, gamma radionuclide analysis of dust collected at three monitoring points at the west gate and boundary of the site (MP-1, 3, 8), at three locations near Units 1 to 4 (north-side slope near Unit 1, west side slope near Units 1 and 2, west-side slope near Units 3 and 4), and on the ocean side of Units 1 to 4 was stopped, changing to observations by continuous dust monitors located inside the site.

For reference: See here for the status of dust monitor measurements near the Fukushima Daiichi Nuclear Power Station site boundary.

Note:also that air sampling for strontium and plutonium analysis, by means of a monitoring car located near the west gate of the site, continues to be conducted once every half year (April and October).

Seawater

Radionuclide analysis is conducted of seawater collected along the coast of the power station and near the water intakes of Units 1 to 4.

Sampling PlaceEnglish form
12345678910111213141516171819202122232425262728293031

*Results of radionuclide analysis of seawater near power station and near water intakes of Units 1 to 4

Starting April 2, 2019, a change was made to where the seawater radionuclide analysis results are archived for the power station coastline and near the Unit 1 to 4 water intakes. Please see here. (Pages showing seawater analysis results in PDF files archived in the section headed “Monitoring on east side of Unit 1 to 4 turbine buildings and bay” )
Note that graphs and detailed analysis results from remeasuring, and analysis results for other collection points, continue to be archived as in the past.

Results of radionuclide analysis of seawater near south discharge outlets of Units 1 to 4

As of September 2018, a change was made to where the radionuclide analysis results are archived for seawater sampled near the south discharge outlets of Units 1 to 4. Please see here. (Pages showing seawater analysis results in PDF files archived in the section headed “Monitoring on east side of Unit 1 to 4 turbine buildings and bay”)

Seawater at bay entrance (measured by radioactivity monitors)

Starting October 1, 2016, data indicating the latest status in 10-minute intervals is made available in real time.

ALPS treated water sampling

Before diluting and discharging ALPS treated water, the concentrations of radioactive materials, etc., contained in the ALPS treated water are checked at the measurement/confirmation facility to ensure that it satisfies the discharge criteria. In order to ensure the objectivity of the analysis results, the concentrations of radioactive materials are analyzed by a third-party (Japan Atomic Energy Agency) in addition to an external agency commissioned by TEPCO.

Nuclides to be measured and assessed Tritium Nuclides to be checked voluntarily
Discharge criteria The sum of the ratios of the concentration of each radionuclide to the regulatory concentration (sum of the ratios to regulatory concentration limit) less than 1 less than 1 million Bq/L no significant concentrations found of any of the nuclides
Language Pre-discharge analysis results of the water in the measurement/confirmation tanks
English 19 (Group A)
Korean 19 (Group A)
Simplified Chinese 19 (Group A)
Traditional Chinese, Taiwan 19 (Group A)
Traditional Chinese, Hong Kong 19 (Group A)

The water in the discharge vertical shaft and the water in the seawater pipe

For a certain period of time after the commencement of discharge, the flow of ALPS treated water and seawater into the discharge vertical shaft will be halted temporarily before ① the discharge vertical shaft (upper-stream storage) becomes full so that the tritium concentration in the water in the shaft can be measured (analysis value*). At this point we will confirm that the analysis value is consistent with the estimated tritium concentration (calculated value*), and lower than 1,500Bq/liter, which is TEPCO’s limit for discharge into the sea.
Furthermore, during discharge, the tritium concentration in the water in ② the seawater pipe upstream of the discharge vertical shaft will also be measured on a daily basis to confirm that analysis values are consistent with the calculated value, and less than 1,500Bq/liter.

Concentrations of tritium (Discharge vertical shaft)
Analysis Value Comparison with calculated value
Summary The analysis value is consistent with the calculated value, and lower than 1,500Bq/L
  • Analysis value and calculated value contain uncertainties.
    For more details, please see the following materials (pdf)

Language Analysis results of the water in the discharge vertical shaft (Upper-stream storage)
English 4

Korean 4

Simplified Chinese 4

Traditional Chinese, Taiwan 4

Traditional Chinese, Hong Kong 4

Click here for analysis results from third parties (Japan Atomic Energy Agency)

Language Analysis results of the water in the seawater pipe upstream of the discharge vertical shaft (Upper-stream storage)
English 6789101112131415161718192021222324
Korean 6789101112131415161718192021222324
Simplified Chinese 6789101112131415161718192021222324
Traditional Chinese, Taiwan 6789101112131415161718192021222324
Traditional Chinese, Hong Kong 6789101112131415161718192021222324

Quick measurement of seawater

Index, as “Discharge Suspension Level”, has been set in order to determine if the discharge needs to be suspended as the facility operation in the event that sea area monitoring results indicate that the water to be discharged is not dispersing sufficiently.
We have also set an “Investigation Level” as an index for determining actions (inspection of facilities and operating procedures, increased monitoring, etc.) if concentration levels that exceed one half of the aforementioned index (Discharge Suspension Level) are detected. During the monitoring with these indexes, we are in effect raising the detection limit which will allow us to obtain analysis results quicker and ascertain conditions of the sea more rapidly.

Locations within 3km of the power station Locations within a 10km square in front of the power station
Index Not exceed Discharge Suspension Level (700Bq/L)
nor Investigation Level (350Bq/L)*
Not exceed Discharge Suspension Level (30Bq/L)
nor Investigation Level (20Bq/L)*
  • *Suspension Level:

    Index for determining if discharge needs to be suspended.

  •  Investigation Level:

    Index for determining actions (inspection of facilities and operational procedures, increased monitoring, etc.) to be taken before the Discharge Suspension Level is reached.

Language Analysis results of seawater (Measurements to obtain results quickly) Sampling locations
English 12345678910111213141516171819202122232425262728293031
Korean 12345678910111213141516171819202122232425262728293031
Simplified Chinese 12345678910111213141516171819202122232425262728293031
Traditional Chinese, Taiwan 12345678910111213141516171819202122232425262728293031
Traditional Chinese, Hong Kong 12345678910111213141516171819202122232425262728293031

Subdrain water

Radionuclide analysis is conducted of radioactive materials in water collected from subdrains, etc. near the turbine buildings of Units 1 to 6 and the subdrain near the central waste treatment facility.

Subdrain water near turbine building English form
35710121417192124262831
Subdrain water near the centralized waste treatment facility English form
12345678910111213141516171819202122232425262728293031

Subdrain and groundwater drain sampling

Groundwater near buildings is pumped up before it can enter the buildings (measure to minimize increase in contaminated water). Moreover, groundwater flowing toward the sea that has been dammed up by installing an ocean-side impermeable wall (measure to prevent contaminated water from leaking) is pumped up, cleaned, and checked for water quality before being discharged into the ocean, in a water treatment facility for subdrain, etc. that went into operation in September 2015. Groundwater that has been pumped up is stored in temporary storage tanks, radioactivity levels are measured, and confirmation is made that it is within operational targets.
To ensure objectivity of the analysis results, radiation level analysis is also conducted by third-party agencies.

Cesium-134 Cesium-137 All beta Strontium Tritium
Operational targets for temporary storage tanks 1Bq/l 1Bq/l 3Bq/l - 1500Bq/l
(For reference) Regulatory limits 60Bq/l 90Bq/l - 30Bq/l 60000Bq/l
WHO guidelines for drinking-water quality 10Bq/l 10Bq/l - 10Bq/l 10000Bq/l

An overview of subdrain initiatives and implementation status is given here.

Temporary storage tank and water collection tank analysis results English form
12344 (Detail)5678101213141516171819202122232425262727 (Detail)28293031
Weighted average sample analysis results
4 (As of July, 2023)27 (As of August, 2023)

Note:Analysis is conducted on water collected before discharge after mixing in the same ratio as that of discharged water each time to all discharged water for that month.

Analysis results for discharged water English form

The most recent data is from September 29, 2023.

Transfer tank analysis results : The most recent data is from June 14, 2016. (English form)

Groundwater bypass-related sampling

As a measure for minimizing the increase in contaminated water, a groundwater bypass went into operation in May 2014, by which groundwater on the mountain side is pumped up before it can enter buildings and its water quality is confirmed before it is discharged into the ocean. Groundwater that has been pumped up is stored in temporary storage tanks, radiation levels are measured, and confirmation is made that it is within operational targets.
To ensure objectivity of the analysis results, radiation level analysis is also conducted by third-party agencies.

Cesium-134 Cesium-137 All beta Strontium Tritium
Operational targets for temporary storage tanks 1Bq/l 1Bq/l 5Bq/l - 1500Bq/l
(For reference) Regulatory limits 60Bq/l 90Bq/l - 30Bq/l 60000Bq/l
WHO guidelines for drinking-water quality 10Bq/l 10Bq/l - 10Bq/l 10000Bq/l

An overview of the groundwater bypass initiative and implementation status is given here, along with related materials.

Pumping well analysis results English Form
See here for maximum values.
247911141618212525 (2)2830
Temporary storage tank analysis results English Form
33 (Detail)916233131 (Datal)
Weighted average sample analysis results English Form
3 (As of July, 2023)31 (As of August, 2023)
Analysis results for discharged water English Form

The most recent data is from September 29, 2023.

Monitoring for tank leakage

In response to leakage from a bottom flange of Tank No. 5 in the I group of the H4 tank area discovered in August 2013, dripping from an upper top plate of a B south area tank (B-A5) occurring in October 2013, and leakage from a flange of an upper top plate of the C1 tank in the H6 tank area occurring in February 2014, ongoing sampling has been implemented to monitor the effects of such leakage. This sampling is conducted near the south discharge outlets of the Fukushima Daiichi Nuclear Power Station, the discharge channels on the site premises, and around the H4 area tanks.

Observation holes around the H4 tank area English Form
See here for maximum values.
5121926
Observation holes around the H6 tank area English Form
See here for maximum values.
5121926

South discharge outlets and discharge channels

Note:Starting September 2018, a change was made to where the analysis results are archived for the south discharge outlets and discharge channels.
See here for the analysis results for the south discharge outlets. See here for the analysis results for the discharge channels.

Monitoring on east side of Unit 1 to 4 turbine buildings and bay

Radionuclide analysis is conducted of groundwater on the east side of Unit 1 to 4 turbine buildings and of seawater in the bay, for confirming sources of radioactive materials in groundwater and their diffusion status, and for monitoring impact on the ocean.

English Form
See here for maximum values.
123456 (See Highest Dose)78910 (See Highest Dose)11 (See Highest Dose)1213 (See Highest Dose)141516 (See Highest Dose)17 (See Highest Dose)1819 (See Highest Dose)202122 (See Highest Dose)2324 (See Highest Dose)25262728293031 (See Highest Dose)

Sampling data from discharge channels on the premises of the Fukushima Daiichi Nuclear Power Station

Monitoring of each of the discharge channels continues, since rainwater flows into the channels after falling on the turbine building roofs, which were contaminated by fallout at the time of the accident.

English Form
See here for maximum values.
12345678910111213141516171819202122232425262728293031

Analysis results for underground reservoirs

In response to the external leaking of water stored in an underground reservoir, occurring in April 2013, impact on the surroundings is being monitored, analyzing groundwater at leak detection holes installed next to the reservoirs and observation holes around them.
Note that the amount of underground reservoir leakage was thereafter assessed to be around 20 to 30 liters.

English Form

Other

Sampling of sprinkled water that has been treated in rainwater treatment equipment after being dammed in tank area

Rainwater dammed in the tank area, after being treated using the reverse osmosis (RO) desalination and other systems, since May 2014 has been sprinkled on the premises of the Fukushima Daiichi Nuclear Power Station. To confirm the impact of this sprinkling, levels of radioactive materials in the treated water (sprinkled water) and in the air at the sprinkling locations, and the surrounding air dose rates, are analyzed.
The most recent data is from June 14, 2016. (English Form)

Detailed analysis results of groundwater around Unit 1 to 4 buildings

In purification testing of wells (subdrain pits) adjacent to Unit 1 to 4 buildings, radioactive materials were detected in water accumulated in the pits. Given the possibility that the source of this radiation is from fallout, new observation pits were installed near Unit 1 to 4 buildings, and fallout is being monitored.
The most recent data is from October 1, 2014.

Water Treatment Equipment Analysis Results

English Form

31

Fish, Shellfish and Seaweed Analysis Results
(waters within 20 km of Fukushima Daiichi Nuclear Power Station)

At the time of the accident, highly concentrated contamination in the basement of the turbine building flowed into the port through underground trenches. Therefore, we analyze fish and shellfish sampled within a 20 km radius around the power station in order to check the effects of cesium on fish and shellfish and the trends.
In accordance with the government‘s policy on the water treated with multi-nuclide removal equipment etc., we have strengthened monitoring of fish and seaweed since April 2022 in order to continuously check the diffusion status centered around tritium into the sea and the conditions of marine organisms. We have increased the number of locations, targets and frequency for measurement, and set detection limits (lower detection limits) to be in line with national targets. Please click here for details.

Sampling Place