Major Maintenance Plan for the Transmission and Transformation Facilities

Print

As of the end of FY2022

  Project Name Voltage(kV) Scale Start of Operation
Transmission
Updating of Goi Thermal Power Plant line 275 11.1km October 2023
New installation of Chiba-Inzai line 275 No1:10.5km
No2:10.5km
April 2024
Switch of the connection of Kashima-Kaihin line 275 0.2km → 0.3km No1 : Apr 2025
No2 : Nov 2024
Discontinuance of No1, 2 of Kashima Thermal Power Plant line 275 5.0km December 2024
Switch of the connection of Fukushima trunk line, mountain-side line 500 1.1km No1 : Jan 2025
No2 : Apr 2025
New installation of MS18GHZ051500 access line (tentative name) 275 0.1km June 2025
New installation of Chiba-Inzai line 275 No.3:10.5km
No.4:10.5km
No3 : Feb 2027
No4 : Nov 2025
New installation of Higashishimizu line 275 18.8km
(Including 6.4km of existing)
January 2027
New installation of Shin-Sodegaura line 500 0.1km No1 : Mar 2027
No2 : Feb 2028
Updating of Higashi-Shinjuku line 275 No2:23.4km→5.0km
No3:23.4km→5.3km
No2 : Nov 2032
No3 : Dec 2027
Updating of Shinjuku line 275 No1:22.1km→21.2km
No2:19.9km→21.2km
No3:19.8km→21.2km
No1 : Aug 2030
No2 : Nov 2032
No3 : Dec 2027
New installation of G5100026 transmission line (tentative name) 500
0.7km December 2028
New installation of Jyohoku line 275 20.9km February 2030
Substation
Increase in capacity of transformer (Shin-Keiyo substation) 275/154 450MVA
Increase in capacity of transformer (Shin-Noda substation) 275/154 80MVA November 2023
Discontinuance of transformer (Kita-Tokyo substation) 275/154 -300MVA January 2022
New construction of Chiba-Inzai substaion 275/66 600MVA April 2024
Additional installation of transformer (Kashima subsation) 275/66 300MVA
Discontinuance of transformer (Ageo substation) 275/66 -300MVA June 2024
Increase in capacity of transformer (Naka-Tokyo substation) 275/154 200MVA 1B : Jan 2025
2B : Jun 2025
Discontinuance of transformer (Shin-Fuji substation) 275/154 -200MVA April 2025
Additional installation of Chiba-Inzai line 275/66 600MVA 4B : Nov 2025
1B : Feb 2027
Increase in capacity of transformer (Kashima subsation) 275/66 200MVA 7B : Feb 2026
8B : Feb 2027
Additional installation of transformer (Shin-Toyosu subsation) 275/66 300MVA March 2026
Increase in capacity of transformer (Shin-Tokorozawa substation) 500/275 1,000MVA 4B : Apr 2026
5B : Jun 2027
Additional installation of transformer (Toyooka subsation) 275/154 450MVA June 2026
Increase in capacity of transformer (Koto substation) 275/66 150MVA June 2026
Increase in capacity of transformer (Kita-Tama substation) 275/66 200MVA 2B : Jun 2026
3B : Jun 2027
Additional installation of transformer (Shin-Fuji subsation) 500/154 750MVA February 2027
Additional installation of transformer (Kita-Sagami subsation) 275/66 600MVA 4B : Jun 2026
8B : Jun 2027
Discontinuance of transformer (Shin-Tokorozawa substation) 500/275 -1,000MVA December 2027

(Note)

  1. Transmission scale: Horizontal distance, Substation scale: increase of output

to TOP

  • facebook
  • twitter
  • tinstagram
  • YouTube