search

Project for the Expansion and Promotion of a Power Distribution Equipment Planning System in Vietnam

Project Overview

We carried out a pilot project with the aim of providing Hanoi Power Corporation with the know-how required for system planning and operation of Japanese power distribution systems. As a result, we arrived at the conclusion that such efforts can yield positive effects on investment and supply reliability. In the future, we are planning to introduce Japanese power distribution systems to Hanoi Power Corporation and other power distribution companies in Vietnam.

  • Pilot feeders

  • Briefing session

  • Power distribution voltage: 35 kV, 22 kV/400, 200 V

1. Name Project for the Expansion and Promotion of a Power Distribution Equipment Planning System in Vietnam
2. Period of implementation From March 2016 to December 2017 (22 months)
(Extended until June 2018)
3. Target Vietnam
4. Content
  1. Implementation of decision-making support software (DSS) for power distribution equipment planning
  2. Implementation of a supervisory control and data acquisition (SCADA) system for monitoring power distribution lines
  3. Implementation of a power distribution management system (DMS)

to TOP

  1. HOME
  2. Our Business
  3. Consulting
  4. Project for the Expansion and Promotion of a Power Distribution Equipment Planning System in Vietnam
  • facebook
  • twitter
  • tinstagram
  • YouTube