We are announcing the status of major inspections and restoration works and
nonconformances at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after
the Niigata-Chuetsu-Oki Earthquake.
1. Inspection/Restoration Status
○ Inspection and restoration completed between April 25th to May 8th, 2008
(Completed on the following date)
Unit No.2 Pressure suppression chamber inspection:
April 29th
Unit No.2 Main transformer inspection (on-site transportation):
May 6th
Unit No.5 House transformers inspection (5A) (on-site transportation):
April 29th
Unit No.5 Excitation transformers inspection (on-site transportation):
April 29th
Restoration work for filtrate tank No.3 and No.4 (No.4 water leakage test):
April 23rd*
○ Inspection and restoration to be commenced between May 9th to May 15th, 2008
(To be commenced on the following date)
Unit No.1 Main transformer inspection (preparation for on-site transportation):
May 9th
Unit No.3 Main transformer inspection (preparation for transportation into
the factory):
May 12th
Unit No.3 Main generator inspection (transportation of rotor):
May 15th
Unit No.4 Stack inspection (detailed inspection for top of stack):
May 8th*
Unit No.6 Turbine inspection (detailed inspection for high pressure turbine and
low pressure turbine (A) (B) and (C)):
May 12th
Unit No.6 Main transformer inspection (carrying in and installation work):
April 30th*
On-site check/inspection/restoration of the oil protection bank for the transformer
(Unit No.3 Recovery of oil-contaminated soil):
May 9th
Restoration and reinforcement work for on-site and outside roads, slope, etc.
(preparation work for reinforcement):
April 30th*
Outdoor fire protection system piping to be placed above ground, installation of
fire protection tank, etc. (Arahama-side: work on installing fire protection system
piping above ground):
April 28th*
* Work schedules added this week.
○ Work Schedule of Major Inspection/Restoration from May 4th to May 31st, 2008
Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
....Appendix
2. Nonconformances Found in the Inspection and Restoration Works Performed after the
Niigata-Chuetsu-Oki Earthquake
Based on the "Public Announcement Regarding Nonconformance Found in the Inspection
and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo
Electric Power Company, Incorporated (TEPCO) provides this announcement containing
incidents information reported from April 24th to May 7th, 2008.
○ Incidents Information (relating to the Chuetsu-Oki Earthquake)
|
<Reports from Apr. 24 to May 7, 2008>
|
○ Other Findings
Unit No.7:
Partial breakages were found on forks of 2 rotor blades on the turbine-side of 14th
stage of the low-pressure turbine (B) and (C). Investigation of the causes and
detailed inspection are going on (announced on March 13th, March 19th, March 27th,
April 3rd, April 10th and April 17th, 2008).
No damage was found based on visual inspection for forks of 512 rotor blades on the
15th and 16th stage of the low-pressure turbine (B), both of which have the same
structure as those forks of rotor blades on the 14th stage (15th stage: 126 blades
each on generator-side and turbine-side; 16th stage: 130 blades each on generator-side
and turbine-side).
Non-destructive inspection conducted for forks of 260 rotor blades of 16th stage of
the low-pressure turbine (B) resulted in indications on the fork of 18 rotor blades on
the generator-side and 19 rotor blades on the turbine-side.
Investigation on the cause of the damages and the indications on the forks of rotor
blades will be continued. Non-destructive inspection for forks of rotor blades on the
15th stage of the low-pressure turbine (B) will also be conducted.
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
(PDF 178KB)
|