search



Corporate Information

 
Press Release (Apr 17,2008)
Nonconformances Found in the Inspection and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake (April 17th)
We are announcing the status of major inspections and restoration works and 
nonconformances at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after 
the Niigata-Chuetsu-Oki Earthquake.  

1. Inspection/Restoration Status

 ○  Inspection and restoration completed between April 11th to April 17th, 2008.
    (Completed on the following date) 

 • Unit No.3 Fuel and control rod inspection (visual inspection of fuels): 
     April 17th 
 • Unit No.3 Fuel and control rod inspection (visual inspection of control rod): 
     April 11th 
 • Unit No.3 Fuel and control rod inspection (visual inspection of channel box): 
     April 11th 
 • Unit No.6 House transformer (6A, 6B) inspection (carrying in): 
     April 12th 
 • Unit No.6 500 kV power cable (OF cable) inspection (energization for testing 
   without load):
     April 12th 
 • Unit No.7 Fuel and control rod inspection (inspection of spent fuel pool rack 
   etc.): 
     April 15th 

 ○   Inspection and restoration to be commenced between April 18th to April 24th, 2008  
     (To be commenced on the following date)  

 • Unit No.1 Fuel and control rod inspection (visual inspection of channel box): 
     April 24th 
 • Unit No.2 Main transformer inspection (preparation for on-site transportation): 
     April 21st 
 • Unit No.2 Excitation transformers inspection (preparation for transportation into 
   factory):
     April 21st
 • Unit No.5 House transformers (5B) inspection (on-site transportation): 
     April 15th*
 • Unit No.5 Main generator inspection (rotor carrying in): 
     April 21st 
 • Unit No.5 Main exhaust duct inspection and restoration (survey prior to restoration 
   work): 
     April 21st 
 • Unit No.6 Main transformer inspection (carrying in and installation work):
     April 22nd 
 • Unit No.6 House transformers inspection (installation work):
     April 14th*
 • House boilers (Arahama-side; 1A, 2A and 2B) inspection (restoration work): 
     April 8th*
 • Restoration and reinforcement work for on-site and outside roads, slope, etc. 
   (preparation work for reinforcement): 
     April 23rd
                                                        * Work schedules added this week

 ○  Work Schedule of Major Inspection/Restoration from April 13th to May 10th, 2008

  • Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear 
    Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
                                                                          ....Appendix

2. Nonconformances Found in the Inspection and Restoration Works Performed after 
   the Niigata-Chuetsu-Oki Earthquake

   Based on the "Public Announcement Regarding Nonconformance Found in the Inspection 
   and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo 
   Electric Power Company, Incorporated (TEPCO) provides this announcement containing 
   incidents information reported from April 10th to April 16th, 2008.

○ Incidents Information (relating to the Chuetsu-Oki Earthquake)
Incidents Information (relating to the Chuetsu-Oki Earthquake)
<Reports from Apr. 10 to Apr. 16, 2008>
Reports from Apr. 10 to Apr. 16, 2008
○ Other Findings • Unit No.7: Partial breakages were found on forks of 2 rotor blades on the turbine-side of 14th-stage of the low-pressure turbine (B) and (C). Investigation of the causes and detailed inspection are going on. Non-destructive inspection was conducted for fixtures of rotor fork of the 14th-stage of the low-pressure turbine (A), (B) and (C) (announced on March 13th, March 19th, March 27th, April 3rd and April 10th, 2008). As a result, indication was not found. Investigation on the cause of the damages and the indication will be continued as well as the visual inspection and non-destructive inspection for forks of rotor blades on the 15th and 16th stages of the low-pressure turbine (B) which have the same structure as forks of rotor blades on 14th stage.

Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear 
          Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
                                                                               (PDF 254KB)
back to page top


to TOP