We are announcing the status of major inspections and restoration works and
nonconformances at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after
the Niigata-Chuetsu-Oki Earthquake.
1. Inspection/Restoration Status
○ Inspection and restoration completed between March 14th to March 19th, 2008.
(Completed on the following date)
Unit No.2 Fuel and control rod inspection (visual inspection of control rod):
March 17th
Unit No.2 Fuel and control rod inspection (inspection of spent fuel pool rack
etc.):
March 19th
Unit No.5 Excitation transformers inspection (internal inspection):
March 17th
Unit No.6 Fuel and control rod inspection (visual inspection of fuel):
March 17th
Unit No.7 Reactor well inspection (confirmation of leakage):
March 15th
Restoration work for solid waste storage facility (Drum soundness verification
work):
March 17th
○ Inspection and restoration to be commenced between March 20th to March 26th, 2008
(To be commenced on the following date)
Unit No.2 Pressure suppression chamber inspection:
March 25th
Unit No.2 House transformer (2A, 2B) inspection (preparation for transportation
into the factory):
March 24th
Unit No.3 Pressure suppression chamber inspection (preparation):
March 20th
Unit No.3 Fuel and control rod inspection (visual inspection of channel box):
March 20th
Unit No.3 Stack inspection (inspection for substructure of piles):
March 24th
Unit No.4 Fuel and control rod inspection (visual inspection of fuel)
March 21st
Unit No.5 Fuel and control rod inspection (visual inspection of control rod):
March 24th
Unit No.6 Reactor internal pump input transformer inspection (installation):
March 26th
Unit No.7 House transformer (7A, 7B) inspection (preparation for carrying in):
March 21st
Unit No.7 House transformer (7A) inspection (installation):
March 24th
Unit No.7 Reactor internal pump input transformer inspection (carrying in):
March 21st
Unit No.7 Reactor internal pump input transformer inspection (installation):
March 25th
Unit No.7 Stack inspection (internal inspection):
March 24th
Outdoor fire protection system piping to be placed above ground, installation
of fire protection tank, etc. (Ohminato-side: work on installing fire protection
system piping above ground):
March 21st
○ Work Schedule of Major Inspection/Restoration from March 16th to April 12th, 2008
Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
....Appendix
2. Nonconformances Found in the Inspection and Restoration Works Performed after the
Niigata-Chuetsu-Oki Earthquake
Based on the "Public Announcement Regarding Nonconformance Found in the Inspection
and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo
Electric Power Company, Incorporated (TEPCO) provides this announcement containing
incidents information reported from March 13th to March 18th, 2008.
○ Incidents Information (relating to the Chuetsu-Oki Earthquake)
|
<Reports from Mar. 13 to Mar. 18, 2008>
|
○ Other Findings
Unit No.7:
As for the inspection for forks of the 14th-stage rotor blades of the low-pressure
turbine (C), damage was found on a part of one rotor blade on March 3rd, 2008.
Detailed inspection to verify the soundness of the relevant part has been conducted
since March 7th, 2008, and based on visual inspection, no additional damage was
found (announced on March 13, 2008)
Subsequently, non-destructive inspection was conducted for forks of 151 rotor blades
except for the one already found to be damaged. As a result, indications were found
on the fork of 17 rotor blades. Investigation on the cause of the indication will be
conducted as well as visual and non-destructive inspection for other forks of the
14th-stage rotor blades of the low-pressure turbine (A), (B) and (C).
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)