Top > Releases ・ Announcements > Press Releases > 2013 > Amendment to Submission of a Request to Change the "Implementation Plan of the Measures for the Specified Reactor Facilities at Fukushima Daiichi Nuclear Power Station"

Press Releases 2013

Press Release (Oct 21, 2013)Amendment to Submission of a Request to Change the "Implementation Plan of the Measures for the Specified Reactor Facilities at Fukushima Daiichi Nuclear Power Station"

On November 7, 2012, we received a document* "Submission of an implementation plan of the measures for the specified reactor facilities to be installed at Fukushima Daiichi Nuclear Power Station" from the Nuclear Regulation Authority. In accordance with the document received, we put together a measure implementation plan and submitted it to the Regulation Authority on December 7, 2012.
Later, the implementation plan had been reviewed by the Nuclear Regulation Authority, and was approved on August 14, 2013.

(Previously announced on November 7, December 7, 2012 and August 14, 2013)

A request to change the implementation plan has been submitted to the Nuclear Regulation Authority on September 13, 2013 (previously announced), and an amendment to the request to change the implementation plan was submitted to the Nuclear Regulation Authority today (on October 21).

Provided below is the outline of the change to be made.

- Implementation plan of the measures for the specified reactor facilities at Fukushima Daiichi Nuclear Power Station
II. Design of the specified reactor facilities
2.5 Contaminated water treatment facilities, etc.
Adjustment to the statement concerning the high-concentration contaminated water treatment facilities at seawater piping trench for Unit 2 and 3

Attachment
- Implementation plan of the measures for the specified reactor facilities at Fukushima Daiichi Nuclear Power Station
II. Design of the specified reactor facilities
2.5 Contaminated water treatment facilities, etc.(PDF 3.75MB)

*Document
"Submission of an implementation plan of the measures for the specified reactor facilities to be installed at Fukushima Daiichi Nuclear Power Station"

The aforementioned documents are available only in Japanese. We apologize for the inconvenience this may cause.