The following is a summary of the procedures covering all phases of the procurement process - from the introduction of your company's to TEPCO to completion of a purchase transaction.
Go To Standard procurement procedure
Introduction of Potential Products from Suppliers
|
v
Submission of Company and Product Information Form
|
v
Classification into Access I to IV
|
v
Confirmation of potential procurement of the Product
|
v
---------------------------------------------------
Access I-B
+--------------------------|
| v
| Disclosure of TEPCO Specifications,
| as necessary ( Conclusion of Nondisclosure Agreement )
| |
| v
+-> Submission of Registration Application Form
Submission of Materials for Document Inspection
|
v
Document Inspection
|
v
Supplier Registration
|
v
---------------------------------------------------
Request for Estimates, Estimate Submission
|
v
Fixing Contract Price and Awarding Contract
|
v
Concluding Contract
|
v
Product Delivery, Inspection, and Payment |
Power Facilities-Related | Boiler systems, Turbine systems, Instrumentation and control equipment, Water screens(trash removing equipment), Water treatment facilities, Flu gas desulfurization and denigration facilities, etc. |
Power Transmission Facilities-Related | Transformers for power transmission, Gas insulated switchgears, Protective relays,etc. |
Telecommunications-Related | Parabolic antennas, Portable transceivers, Optical cable, etc. |
Line and Cable-Related | Pipe-type oil-filled cable, 275kV oil-filled cable, etc. |
© Tokyo Electric Power Company Holdings, Inc.