Top > Releases ・ Announcements > Fukushima Daiichi NPS Prompt Report > 2013 > Immediate release:Second fuel removal work safely completed at Fukushima Daiichi NPS
Video explaining the fuel removal operation describes the workers' tremendous efforts towards the safer storage of fuel assemblies inside the common pool
Fukushima, Japan, Dec. 2, 2013 - TEPCO announced that they have successfully completed the storage of all 22 spent fuel assemblies, which were transported from the Unit 4 spent fuel pool, inside the safer, common pool at Fukushima Daiichi NPS.
The fuel assemblies were loaded into the transportation cask from November 26 to 27, and transported to the common pool building on November 29. On November 30, work to transfer the assemblies to the fuel rack inside the common pool started at 1:00PM and completed at 5:03PM without incident.
The removal of all fuel inside the Unit 4 spent fuel pool is planned to take until the end of 2014.
Video explaining the fuel removal operation:
http://photo.tepco.co.jp/en/date/2013/201312-e/131202-01e.html
Video and photos of the second fuel removal work at the common pool:
http://photo.tepco.co.jp/en/date/2013/201311-e/131129-01e.html
Video of the extraction of spent fuel from Unit 4, taken underwater:
http://photo.tepco.co.jp/en/date/2013/201311-e/131127-01e.html
Video explaining the removal process/Dr. Klein's comments and material explaining an overview of the task:
http://photo.tepco.co.jp/en/date/2013/201310-e/131030-02e.html
President Hirose's comments regarding the start of fuel removal: