Press Release (Sep 13, 2013)Submission of a Request to Change the "Implementation Plan of the Measures for the Specified Reactor Facilities at Fukushima Daiichi Nuclear Power Station"

On November 7, 2012, we received a document* "Submission of an implementation plan of the measures for the specified reactor facilities to be installed at Fukushima Daiichi Nuclear Power Station" from the Nuclear Regulation Authority. In accordance with the document received, we put together a measure implementation plan and submitted it to the Regulation Authority on December 7, 2012.
Later, the implementation plan had been reviewed by the Nuclear Regulation Authority, and was approved on August 14, 2013.

(Previously announced on November 7, December 7, 2012 and August 14, 2013)

A request to change the implementation plan has been submitted to the Nuclear Regulation Authority today (on September 13).

Provided below is the outline of the change to be made.

- Implementation plan of the measures for the specified reactor facilities at Fukushima Daiichi Nuclear Power Station
I. Overall schedule of installing the specified reactor facilities and risk evaluation
 1.1 Schedules at Units 1-4
 2.4 Future measures to reduce risks for the specified reactor facilities

II. Design of the specified reactor facilities
 2.5 Contaminated water treatment facilities, etc.
 2.15 Radiation control facilities, etc.

III. Security of the specified reactor facilities
 Part 1 (Security measures for the reactors at Unit 1, 2, 3 and 4)
 Part 2 (Security measures for the reactors at Unit 5 and 6)
 Part 3 (Supplementary explanation of security measures)
  2.1 Management of radioactive waste, etc.
  2.2 Dose evaluation
  3.1 Protection and control of radiation

Attachment
Implementation plan of the measures for the specified reactor facilities at Fukushima Daiichi Nuclear Power Station
I. Overall schedule of installing the specified reactor facilities and risk evaluation
 1.1 Schedules at Units 1-4(PDF 1.41MB)PDF
 2.4 Future measures to reduce risks for the specified reactor facilities(PDF 225KB)PDF

II. Design of the specified reactor facilities
 2.5 Contaminated water treatment facilities, etc.(PDF 3.67MB)PDF
 2.15 Radiation control facilities, etc.(PDF 236MB)PDF

III. Security of the specified reactor facilities
 Part 1 (Security measures for the reactors at Unit 1, 2, 3 and 4)
  Submission of a request to change (1)(PDF 913KB)PDF
  Submission of a request to change (2)(PDF 981KB)PDF
 Part 2 (Security measures for the reactors at Unit 5 and 6)(PDF 2.34MB)PDF
 Part 3 (Supplementary explanation of security measures)
  2.1 Management of radioactive waste, etc.(PDF 305KB)PDF
  2.2 Dose evaluation(PDF 768KB)PDF
  3.1 Protection and control of radiation(PDF 427KB)PDF

<Reference> Submission of a Request to Change the "Implementation Plan of the Measures for the Specified Reactor Facilities at Fukushima Daiichi Nuclear Power Station"(PDF 106KB)PDF

*Document
"Submission of an implementation plan of the measures for the specified reactor facilities to be installed at Fukushima Daiichi Nuclear Power Station"

The aforementioned documents are available only in Japanese. We apologize for the inconvenience this may cause.

In Order to view the PDF documents, you will need a software product called Adobe® Acrobat® Reader installed on your computer. You can download this software product for free from Adobe's Web site by clicking the left button:


to TOP