Top > Releases ・ Announcements > Fukushima Daiichi NPS Prompt Report > 2013 > Oil Leakage from Unmanned Heavy Equipment for Debris Removal in Upper Part of Unit 3 Reactor Building at Fukushima Daiichi Nuclear Power Station (Follow-up Information)
This is follow-up information on the oil leakage from unmanned heavy equipment, which occurred today (July 10).
We inspected the heavy equipment, and found hydraulic oil oozing at the hydraulic hose joint. We covered this part with a protective material against oil, and no oil has been found that dropped to the floor surface of Unit 3 Reactor Building from this covered part.
© Tokyo Electric Power Company Holdings, Inc.