search


Top > Releases ・ Announcements > Fukushima Daiichi NPS Prompt Report > 2013 > Water Leak from the Underground Reservoirs in Fukushima Daiichi Nuclear Power Station (Follow-up Information No.186)

Fukushima Daiichi NPS Prompt Report 2013

Fukushima Daiichi NPS Prompt Report (May 31, 2013)Water Leak from the Underground Reservoirs in Fukushima Daiichi Nuclear Power Station (Follow-up Information No.186)

This is follow-up information regarding the water leak from the underground reservoirs at Fukushima Daiichi NPS.

The results of sampling performed in the underground reservoirs yesterday (May 30) are as follows.
- Drain holes of the underground reservoirs No.1-7
- Leakage detection holes of the underground reservoirs No.1-4 and 6
- Observation holes of the underground reservoirs (around reservoirs No.1-3): A1-A19
- Observation holes of the underground reservoirs (around reservoir No.6): B1-B3

No significant change was found with the results compared to the previous results obtained on May 29.

Please visit our web page for the sampling results.
http://www.tepco.co.jp/en/nu/fukushima-np/f1/smp/index-e.html

The water level, etc. of the underground reservoirs will continue to be intensively monitored.


to TOP