Top > Releases ・ Announcements > Fukushima Daiichi NPS Prompt Report > 2013 > Water Leak from the Underground Reservoirs in Fukushima Daiichi Nuclear Power Station (Follow-up Information No.183)
This is follow-up information regarding the water leak from the underground reservoirs at Fukushima Daiichi NPS.
The results of sampling performed in the underground reservoirs yesterday (May 29) are as follows.
- Drain holes of the underground reservoirs No.1-7
- Leakage detection holes of the underground reservoirs No.1-4 and 6
- Observation holes of the underground reservoirs (around reservoirs No.1-3): A1-A19
- Observation holes of the underground reservoirs (around reservoir No.6): B1-B3
No significant change was found with the results compared to the previous results obtained on May 28.
The results of tritium sampling performed on May 22 (analysis performed once a week) are as follows.
- Drain holes of the underground reservoirs No.1-4 and 6
- Leakage detection holes of the underground reservoirs No.1-4 and 6
No significant change was found with the tritium analysis results compared to the previous results.
Please visit our web page for the sampling results.
http://www.tepco.co.jp/en/nu/fukushima-np/f1/smp/index-e.html
The water level, etc. of the underground reservoirs will continue to be intensively monitored.