Fukushima Daiichi NPS Prompt Report (May 23, 2013)Water Leak from the Underground Reservoirs in Fukushima Daiichi Nuclear Power Station (Follow-up Information No.168)

This is follow-up information regarding the water leak from the underground reservoirs at Fukushima Daiichi NPS.

An alternating transfer between the underground reservoir No.3 and the underground reservoir No.6 to G6 tank will be conducted since they are sharing the same transfer line.

The water transfer from the underground reservoir No.6 to G6 area tank was started at 10:19 AM on May 21 but temporarily suspended at 4:02 PM today (May 23).

The transfer line will be switched from the underground reservoir No.6 to the underground reservoir No.3 and the water transfer from the underground reservoir No.3 to G6 area tank will be restarted on May 25.