Top > Releases ・ Announcements > Fukushima Daiichi NPS Prompt Report > 2013 > Water Leak from the Underground Reservoirs in Fukushima Daiichi Nuclear Power Station (Follow-up Information No.112)
This is follow-up information regarding the water leak from the underground reservoirs at Fukushima Daiichi NPS.
Following the suspension of water transfer from the underground reservoir No.1 to the filtrate water tank No.1 at 5:12 AM today (April 29), the water transfer from the underground reservoir No.1 to H2 area tank was restarted at 9:23 AM today.
As a result of patrol on the water transfer status, no abnormality such as leakage has been found.
The water transfer from the underground reservoir No.1 to H2 area tank is planned to be performed during day time.
© Tokyo Electric Power Company Holdings, Inc.