Top > Releases ・ Announcements > Fukushima Daiichi NPS Prompt Report > 2013 > Water Leak from the Underground Reservoirs in Fukushima Daiichi Nuclear Power Station (Follow-up Information No.37)
This is follow-up information regarding the water leak from the underground reservoirs at Fukushima Daiichi NPS.
Regarding the leakage from the connection part (flange) of the transfer pump outlet pipe which occurred during water transfer from the underground reservoir No.3 to No.6, the pipe flange will be disassembled in order to investigate the cause of the leakage.
Also, we will start removing the soil covering the upper part of the underground reservoir (embankment) where the leaked water has been absorbed.
© Tokyo Electric Power Company Holdings, Inc.