Top > Releases ・ Announcements > Fukushima Daiichi NPS Prompt Report > 2013 > Water Leak from the Underground Reservoirs in Fukushima Daiichi Nuclear Power Station (Follow-up Information No.23)

Fukushima Daiichi NPS Prompt Report 2013

Fukushima Daiichi NPS Prompt Report (Apr 09, 2013)Water Leak from the Underground Reservoirs in Fukushima Daiichi Nuclear Power Station (Follow-up Information No.23)

This is follow-up information regarding the water leak from the underground reservoirs at Fukushima Daiichi NPS.

The results of sampling performed in the leakage detection hole (at 2 locations) and the drain hole (at 2 locations) of the underground reservoir No.1 are as follows.

- Water in the leakage detection hole (in the northeast side) of the underground reservoir No.1
Sampling performed at 8:35 AM on April 9
Chloride concentration: 910ppm (previously announced)
Iodine 131: Below the detection limit (1.3×10^-1 Bq/cm3)
Cesium 134: Below the detection limit (1.8×10^-1 Bq/cm3)
Cesium 137: Below the detection limit (9.7×10^-2 Bq/cm3)
Antimony 125: 1.8×10^1 Bq/cm3
Ruthenium 106: 1.2×10^0 Bq/cm3
All β: 1.0×10^4 Bq/cm3

Sampling performed at 1:40 PM on April 9
Chloride concentration: 1100ppm (previously announced)
Iodine 131: Under analysis
Cesium 134: Under analysis
Cesium 137: Under analysis
All β: Under analysis

- Water in the leakage detection hole (in the southwest side) of the underground reservoir No.1
Sampling performed at 8:30 AM on April 9
Chloride concentration: 8ppm (previously announced)
Iodine 131: Below the detection limit (2.8×10^-2 Bq/cm3)
Cesium 134: Below the detection limit (5.0×10^-2 Bq/cm3)
Cesium 137: Below the detection limit (6.9×10^-2 Bq/cm3)
All β: Under analysis

Sampling performed at 1:20 PM on April 9
Chloride concentration: 9ppm (previously announced)
Iodine 131: Under analysis
Cesium 134: Under analysis
Cesium 137: Under analysis
All β: Under analysis

- Water in the drain hole (in the northeast side) of the underground reservoir No.1
Sampling performed at 6:30 AM on April 9
Chloride concentration: 12ppm
Iodine 131: Below the detection limit (2.9×10^-2 Bq/cm3)
Cesium 134: Below the detection limit (5.0×10^-2 Bq/cm3)
Cesium 137: Below the detection limit (6.9×10^-2 Bq/cm3)
All β: Under analysis

- Water in the drain hole (in the southwest side) of the underground reservoir No.1
Sampling performed at 6:30 AM on April 9
Chloride concentration: 7ppm
Iodine 131: Below the detection limit (2.8×10^-2 Bq/cm3)
Cesium 134: Below the detection limit (5.1×10^-2 Bq/cm3)
Cesium 137: Below the detection limit (6.8×10^-2 Bq/cm3)
All β: Under analysis

Please refer to the document on iodine and cesium radioactivity analysis results available in our web page.
URL: http://www.tepco.co.jp/en/nu/fukushima-np/f1/smp/index-e.html