Top > Releases ・ Announcements > Fukushima Daiichi NPS Prompt Report > 2013 > Water Leak from the Underground Reservoir No.2 in Fukushima Daiichi Nuclear Power Station (Follow-up Information No.5)
This is follow-up information regarding the water leak from the underground reservoir No. 2 in Fukushima Daiichi NPS.
Since 5:43 am on April 6, we have been transferring the water from the underground reservoir No. 2 to the underground reservoir No. 1 utilizing the three temporary pumps in addition to the pump which started first.
To add one more temporary pump, we temporarily stopped the three temporary pumps at 12:07 pm. The pump which started first is still under operation.