Fukushima Daiichi NPS Prompt Report (Apr 06, 2013)Water Leak from the Underground Reservoir No.2 in Fukushima Daiichi Nuclear Power Station (Follow-up Information No.4)

This is follow-up information regarding the water leak from the underground reservoir No. 2 in Fukushima Daiichi NPS.

At 5:43 am on April 6, we started transferring the water from the underground reservoir No. 2 to the underground reservoir No. 1. In addition, we started operation of the additional three temporary pumps at 9:38 am.

At 9:41 am, we conducted an on-site survey and confirmed that there is no abnormality such as leakage on the transferring line.