Top > Releases ・ Announcements > Press Releases > 2013 > Revision of the "Implementation Plan of Measures to be Taken for the Specified Reactor Facilities at Fukushima Daiichi Nuclear Power Station"
On November 7, 2012, we received a document* "Submission of an implementation plan of the measures to be taken for the specified reactor facilities to be installed at Fukushima Daiichi Nuclear Power Station" from the Nuclear Regulation Authority. In accordance with the document received, we put together a measure implementation plan and submitted it to the Regulation Authority on December 7, 2012.
(Previously announced on November 7 and December 7, 2012)
The implementation plan was revised with necessary changes incorporated based on the government review and has been submitted to the Nuclear Regulation Authority.
The contents related to the following have been added to the implementation plan.
Implementation Plan of Measures to be Taken for the Specified Reactor Facilities at Fukushima Daiichi Nuclear Power Station
I. Overall schedule of installing the specified reactor facilities and risk evaluation
II. Design of the specified reactor facilities
III. Security of the specified reactor facilities
VI. Promotion of understanding of implementation of implementation plan
Attachment
I. Overall schedule of installing the specified reactor facilities and risk evaluation(PDF 1.92MB)
II. Design of the specified reactor facilities(PDF 3.49MB)
III. Security of the specified reactor facilities(PDF 3.50MB)
VI. Promotion of understanding of implementation of implementation plan(PDF 123KB)
*Document
"Submission of an implementation plan of the measures to be taken for the specified reactor facilities to be installed at Fukushima Daiichi Nuclear Power Station"
The aforementioned documents are available only in Japanese. We apologize for the inconvenience this may cause.
© Tokyo Electric Power Company Holdings, Inc.