Submission of the Restoration Plan (Revision 2) in Accordance with the Nuclear Plant Operator's Anti-Disaster Measures Operation Plan for Fukushima Daini Nuclear Power Station and the Interim Progress Report (Restoration Completion of Unit 3)

October 16, 2012
Tokyo Electric Power Company

For the purpose of advancing restoration measures at Fukushima Daini Nuclear Power Station, a restoration plan was developed based on the Nuclear Plant Operator's Anti-Disaster Measures Operation Plan and submitted to the Minister of Economy, Trade and Industry and the governors of Fukushima prefecture, Naraha town and Tomioka town. (Submitted on January 31, 2012 and revised on May 31, 2012)

At Fukushima Daini Power Station, the equipments/facilities necessary for maintaining the cold shutdown condition are being restored in accordance with the restoration plan. Following the restoration completion of Unit 4 on May 17, 2012, restoration of Unit 3 and Unit 3-4 discharge channel monitoring equipment (common facility) has been completed on October 11, 2012 and September 21, 2012 respectively. On October 16, 2012, a progress report including these updates was submitted to the Prime Minister, the Nuclear Regulatory Authority and the governors of Fukushima prefecture, Naraha town and Tomioka town along with the updated restoration plan (revision 2, including the restoration completion of Unit 3).

In accordance with the restoration plan, we will continue our utmost efforts in enhancing the reliability of equipments/facilities necessary to maintain the cold shutdown condition at Fukushima Daiichi Nuclear Power Station.

End

 

Attachments
- Interim Progress Report on the Restoration Plan in Accordance with the Nuclear Plant Operator's Anti-Disaster Measures Operation Plan for Fukushima Daini Nuclear Power Station (Outline)(PDF 135KB)
- Progress Status of the Restoration Plan for Fukushima Daini Nuclear Power Station (Unit 3: As of October 11, 2012)(PDF 14.4KB)
- Interim Progress Report on the Restoration Plan in Accordance with the Nuclear Plant Operator's Anti-Disaster Measures Operation Plan for Fukushima Daini Nuclear Power Station (Restoration Completion of Unit 3)(PDF 1.54MB) (Japanese only)
- Restoration Plan in Accordance with the Nuclear Plant Operator's Anti-Disaster Measures Operation Plan (Revision 2)(PDF 3.13MB)(Japanese only)