search



Corporate Information

 
Press Release (Mar 02,2012)
Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 10:00am, March 2)
  
Due to the Tohoku-Chihou-Taiheiyou-Oki Earthquake which occurred on March 
11, 2011, TEPCO's facilities including our nuclear power stations have 
been severely damaged. We deeply apologize for the anxiety and 
inconvenience caused. 
With regard to the accident at Fukushima Daiichi Nuclear Power Station, on 
April 17, 2011, we have compiled the roadmap towards restoration from the 
accident and on July 19 we accomplished the Step1 target "Radiation dose 
is in steady decline". Then on December 16 we confirmed the accompl 
ishment of the Step 2 target "Release of radioactive materials is under 
control and radiation doses are being significantly held down". 
In addition, on December 21, 2011, we have compiled the "Mid-to-long-Term 
Roadmap toward the Decommissioning of Fukushima Daiichi Nuclear Power 
Units 1-4, TEPCO". 
In addition to the maintenance of the plant's stable condition, we will 
implement Mid-to-Long Term countermeasures towards the decommissioning of 
Fukushima Daiichi Nuclear Power Units 1-4 to enable evacuees to return to 
their homes as soon as possible and reduce the anxiety of the people in 
Fukushima and the whole nation as soon as possible. 
 
Below is the status of TEPCO's major facilities. 
 
*The updates are underlined. 
 
[Nuclear Power Station] 
·Fukushima Daiichi Nuclear Power Station: Unit 1 to 3: shut down due to 
 the earthquake: 
  (Units 4 to 6: outage due to regular inspections before the earthquake) 
 
 -With regard to the water injection volume for Unit 2 reactor, which was 
  increased with temperature figure raising, we have gradually adjusted it 
  to the original volume before temperature increasing (Feed water system: 
  approx. 3.0m3/h, core spray system: approx. 6.0m3/h). During our 
  observing the plant parameter after the decreasing the flow rate of feed 
  water system on February 22, we found that one thermometer in the lower 
  part of the RPV indicated the different movement from others. From 0:21 
  pm to 2:48 pm on February 23, we investigated the concerned device. As 
  the result of the measurement of DC resistance, we found no breaking 
  wire and availability of the thermometer. But we confirmed that the DC 
  resistance of it became higher than the previous measurement test data. 
  We will evaluate the soundness of the concerned device and examine 
  correspondence in future. We make sure no re-criticality state because 
  there were no significant changes at the monitoring post and as the 
  result of the sampling for the Gas Control System of the Unit 2, we 
  confirmed that the concentration of Xe-135 was below the detectible 
  limit. 
   ·At 5:00 am on March 2, the temperature of the lower part of the RPV 
   (top of the lower head 135°) : approx. 44.7 °C 
   ·At 5:00 am on March 2, the temperature of the lower part of the RPV 
   (top of the lower head 270°) : approx. 41.4 °C (reference) 
 
 -As we confirmed that high radioactivity contaminated water is 
  accumulating in the pit of water circulating pump discharge valve of 
  unit 3 pump chamber at the inspection of trench etc. conducted on 
  January 19, we started to transferring accumulated water from the pit to 
  the basement of unit 2 turbine building at 8:26 am, March 1. At 3:18 pm 
  on the same day, we stopped transfer. 
 
 -At 10:00 am on March 1, we start transfer of the accumulated water from 
  the basement of Turbine Building of Unit 6 to the temporary tank. At 
  4:00 pm on the same day, we stopped transfer. 
 
 -In order to conduct the work to improve the reliability of water 
  treatment facilities, we are planning to stop water treatment facilities 
  one after another. At 8:45 am on March 1, we stopped the cesium 
  adsorption apparatus. It will be out of service until March 15. We 
  calculated the estimated water level increase at each building due to 
  the stop o the facilities, and confirmed that the water levels in each 
  building will be maintained within the limits. We also have sufficient 
  volume of treated water, therefore there will be no impact on the water 
  injection to the reactors. At 8:07 am on March 2, we stopped the 2nd 
  Cesium Adsorption Apparatus. 
 
 -At 9:44 am on March 2, in order to conduct the work to switch the 
  control circuits of on-site power source for operation of southern 
  switching station, we cut the power of on-site power source. The 
  evaporation apparatuses of water desalination facilities and 
  desalination facilities (reverse osmosis membrane type) are out of 
  service due to the work to switch the control circuits. We also have 
  sufficient volume of treated water, therefore there will be no impact on 
  the water injection to the reactors. 
 
·Fukushima Daini Nuclear Power Station: 
 Units 1 to 4: shutdown due to the earthquake 
 
·Kashiwazaki Kariwa Nuclear Power Station: 
 Units 6: under normal operation 
  (Units 1 to 5 and 7: outage due to regular inspections) 
 
[Thermal Power Station] 
·Power supply has returned to normal and the facilities damaged by the 
 earthquake are now being handled in a timely manner. 
 
[Hydro Power Station] 
·Power supply has returned to normal and the facilities damaged by the 
 earthquake are now being handled in a timely manner. 
 
[Impacts on Transmission Facilities] 
·Power supply has returned to normal and the facilities damaged by the 
 earthquake are now being handled in a timely manner. 
 
[Impacts on Power Supply and Demand Balance] 
We expect to maintain stable power supply in March. 
Daily supply and demand balance is announced at our "TEPCO Electricity 
Forecast". 
 
 
Appendix: Past Progress (As of 10:00 am on March 2, 2012) (PDF 459KB) 
Appendix: Past Progress (From March 11, 2011 to July 31, 2011) (PDF 225KB) 
 
* Revised past progress 
back to page top


to TOP