Other related documents
The past progress of the "Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake"
The past progress of the "Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake" is only available in Japanese.We apologize for any inconvenience this may cause. The daily "Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake" is updated on "Press Releases".
Marking the First Year since the Fukushima Daiichi Nuclear Power Accident
- Fukushima Daiichi -A One Year Review
- A One-year Review of Fukushima Daiichi Nuclear Power Station "Steps to Achieve Stabilization"
- Report from the site of Fukushima Daiichi Nuclear Power Station (Movie)
Roadmap towards Restoration from the Accident at Fukushima Daiichi Nuclear Power Station
STEP 2 has been completed.
- Archives [Display and non-display]
-
- Nov 17, 2011
Progress status of "Roadmap towards Restoration from the Accident at Fukushima Daiichi Nuclear Power Station" on November 17 - Oct 17, 2011
Progress status of "Roadmap towards Restoration from the Accident at Fukushima Daiichi Nuclear Power Station" on October 17 - Sep 20, 2011
Progress status of "Roadmap towards Restoration from the Accident at Fukushima Daiichi Nuclear Power Station" on September 20 - Aug 17, 2011
Progress status of "Roadmap towards Restoration from the Accident at Fukushima Daiichi Nuclear Power Station" on August 17 - Jul 19, 2011
Progress status of "Roadmap towards Restoration from the Accident at Fukushima Daiichi Nuclear Power Station" on July 19 - Jun 17, 2011
Progress status of the "Roadmap towards Restoration from the Accident at Fukushima Daiichi Nuclear Power Station" - Jun 14, 2011
Outline of the reactor building covering plan and commencement of main construction of Unit 1 at Fukushima Daiichi Nuclear Power Station - Jun 10, 2011
Status of improvement on working environment of workers in Fukushima Daiichi Nuclear Power Station - May 26, 2011
Start of Spray of Dust Inhibitor to the Radioactive Materials around the Turbine Buildings and Reactor Buildings of Unit 1-4 of Fukushima Daiichi Nuclear Power Station - May 17, 2011
Progress status of the "Roadmap towards Restoration from the Accident at Fukushima Daiichi Nuclear Power Station" - May 13, 2011
Commencement of a preparation work for the installation of a cover for the reactor building of Unit 1, Fukushima Daiichi Nuclear Power Station - May 08, 2011
Improvement of Working Environment inside the Reactor Building and Opening the Airlock of Unit 1 of Fukushima Daiichi Nuclear Power Station - May 04, 2011
Improvement of the living environment of the workers at Fukushima Daiichi and Daini Nuclear Power Stations - May 04, 2011
Report Instruction regarding Improvement of the working environment inside the reactor building of Unit 1, Fukushima Daiichi Nuclear Power Station - May 01, 2011
Improvement of the working environment inside the reactor building of Unit 1, Fukushima Daiichi Nuclear Power Station - Apr 30, 2011
Installation of support structure under the spent fuel pool of Unit 4 - Apr 30, 2011
Countermeasures against Tsunami Caused by Aftershocks - Apr 28, 2011
Utilization of Robots (Remote Control Machines) In the Accident of Fukushima Daiichi Nuclear Power Station (PDF 1.62MB) - Apr 27, 2011
Installation Plan of the Water Treatment Facility - Apr 17, 2011
Roadmap towards Restoration from the Accident at Fukushima Daiichi Nuclear Power Station
- Nov 17, 2011
Accomplishments of the International Information Disclosure Activities regarding the Accident at Fukushima Daiichi Nuclear Power Station
TEPCO has disclosed the information to the global community regarding the accident at Fukushima Daiichi Nuclear Power Station through international conferences.