Due to the Tohoku-Chihou-Taiheiyou-Oki Earthquake which occurred on March
11, 2011, TEPCO's facilities including our nuclear power stations have been
severely damaged. We deeply apologize for the anxiety and inconvenience
caused.
With regard to the accident at Fukushima Daiichi Nuclear Power Station, on
April 17, 2011, we have compiled the roadmap towards restoration from the
accident and on July 19 we accomplished the Step1 target "Radiation dose
is in steady decline". Then on December 16 we confirmed the accomplishment
of the Step 2 target "Release of radioactive materials is under control
and radiation doses are being significantly held down".
In addition, on December 21, 2011, we have compiled the "Mid-to-long-Term
Roadmap toward the Decommissioning of Fukushima Daiichi Nuclear Power Units
1-4, TEPCO".
In addition to the maintenance of the plant's stable condition, we will
implement Mid-to-Long Term countermeasures towards the decommissioning of
Fukushima Daiichi Nuclear Power Units 1-4 to enable evacuees to return to
their homes as soon as possible and reduce the anxiety of the people in
Fukushima and the whole nation as soon as possible.
Below is the status of TEPCO's major facilities.
* The updates are underlined.
[Nuclear Power Station]
· Fukushima Daiichi Nuclear Power Station: Unit 1 to 3: shut down due to
the earthquake:
(Units 4 to 6: outage due to regular inspections before the earthquake)
- With regard to the water injection volume for Unit 2 reactor, which
was increased with temperature figure raising, we have gradually
adjusted it to the original volume before temperature increasing (Feed
water system: approx. 3.0m3/h, core spray system: approx. 6.0m3/h).
During our observing the plant parameter after the decreasing the flow
rate of feed water system on February 22, we found that one thermometer
in the lower part of the RPV indicated the different movement from
others. From 0:21 pm to 2:48 pm on February 23, we investigated the
concerned device. As the result of the measurement of DC resistance,
we found no breaking wire and availability of the thermometer. But we
confirmed that the DC resistance of it became higher than the previous
measurement test data. We will evaluate the soundness of the concerned
device and examine correspondence in future. We make sure no re-
criticality state because there were no significant changes at the
monitoring post and as the result of the sampling for the Gas Control
System of the Unit 2, we confirmed that the concentration of Xe-135
was below the detectible limit.
· At 5:00 am on February 28, the temperature of the lower part of the
RPV (top of the lower head 135°) : approx. 44.3 °C
(Reference)
· At 5:00 am on February 28, the temperature of the lower part of the
RPV (top of the lower head 270°) : approx. 40.8 °C
- At 10:00 am on February 27, we start transfer of the accumulated water
from the basement of Turbine Building of Unit 6 to the temporary tank.
At 4:00 pm on the same day, we stopped transfer. At 10:00 am on February
28, we restarted the transfer.
- As we confirmed that high radioactivity contaminated water is
accumulating in the pit of water circulating pump discharge valve of
unit 3 pump chamber at the inspection of trench etc. conducted on
January 19, we started to transferring accumulated water from the pit
to the basement of unit 2 turbine building at 10:13 am, February 27.
At 3:34 pm on the same day, we stopped transfer. At 8:51 am on February
28, we restarted the transfer.
- At 1:26 pm, on February 27, we started injecting hydrazine [corrosion
inhibitor] into unit 2 spent fuel pool by using circulating cooling
system. At 3:28 pm on the same day, we completed the injection.
· Fukushima Daini Nuclear Power Station:
Units 1 to 4: shutdown due to the earthquake
· Kashiwazaki Kariwa Nuclear Power Station:
Units 6: under normal operation
(Units 1 to 5 and 7: outage due to regular inspections)
[Thermal Power Station]
· Power supply has returned to normal and the facilities damaged by the
earthquake are now being handled in a timely manner.
[Hydro Power Station]
· Power supply has returned to normal and the facilities damaged by the
earthquake are now being handled in a timely manner.
[Impacts on Transmission Facilities]
· Power supply has returned to normal and the facilities damaged by the
earthquake are now being handled in a timely manner.
[Impacts on Power Supply and Demand Balance]
This winter, there are some minus factors such as the regular inspection
of Unit 5 at Kashiwazaki-Kariwa Nuclear Power Station. On the other hand,
there are several plus factors such as the recovery of the common thermal
power stations which suffered the earthquake. As a result, we expect to
secure 53.7 GW (at the end of February) supply power.
Compared to the maximum demand in the last winter, which is 51.5 GW, we
will have 2.2 GW generation reserve margin.
We expect to maintain stable power supply this winter. However, as there
remains possibilities of unplanned shutdowns at our power stations and
growth in the demand according to the rapid change in the temperature, we
would like to ask your reasonable effort to save electricity.
We will continue to make our efforts to maintain stable operation and
maintenance of the power facilities in order to "prevent in principle" the
planned blackouts and secure power supply.
Appendix: Past Progress (As of 10:00 am on February 28, 2012) (PDF 456KB)
Appendix: Past Progress (From March 11, 2011 to July 31, 2011) (PDF 225KB)
* Revised past progress