Due to the Tohoku-Chihou-Taiheiyou-Oki Earthquake which occurred on March
11, 2011, TEPCO's facilities including our nuclear power stations have been
severely damaged. We deeply apologize for the anxiety and inconvenience
caused.
With regard to the accident at Fukushima Daiichi Nuclear Power Station, on
April 17, 2011, we have compiled the roadmap towards restoration from the
accident and on July 19 we accomplished the Step1 target "Radiation dose
is in steady decline". Then on December 16 we confirmed the accomplishment
of the Step 2 target "Release of radioactive materials is under control
and radiation doses are being significantly held down".
In addition, on December 21, 2011, we have compiled the "Mid-to-long-Term
Roadmap toward the Decommissioning of Fukushima Daiichi Nuclear Power Units
1-4, TEPCO".
In addition to the maintenance of the plant's stable condition, we will
implement Mid-to-Long Term countermeasures towards the decommissioning of
Fukushima Daiichi Nuclear Power Units 1-4 to enable evacuees to return to
their homes as soon as possible and reduce the anxiety of the people in
Fukushima and the whole nation as soon as possible.
Below is the status of TEPCO's major facilities.
* Updates are underlined.
[Nuclear Power Station]
· Fukushima Daiichi Nuclear Power Station: Unit 1 to 3: shut down due to
the earthquake:
(Units 4 to 6: outage due to regular inspections before the earthquake)
- From February 2, tendency of temperature rise at the bottom of PCV has
been observed. While we increased the water injection to the reactor
and have been monitoring the trend of the temperature, it is still high
around 70°C. On February 6, we sampled the gas by the gas control
system of Unit 2 Primary Containment Vessel. The density of Xenon 135
at the entrance of the system was below the detection limit. Since it
is below 1Bq/cm3, which is the threshold for judging re-criticality,
we confirmed the reactor didn't go re-critical, however, in order to
avoid the possibility of going re-critical being increased as a result
of the water density in the reactor being increased by rapid injection
of cold water is increased, we injected the boric acid into the reactor
as a safety countermeasure from 0:19 am to 3:20 am on February 7, which
was before we increased the volume of the water injection. At 4:24 am
on the same day, we changed the amount of the core spray system
injection water from 3.7m3/h to 6.7m3/h (the amount of the continuing
feed water system injection is 6.8m3/h). After that, we continued to
monitor the temperature tendency, finding that the temperature slowly
increased. At 10:45 pm on February 11, we changed the water injection
amount through the reactor feed water system from approx. 6.8m3/h to
7.8m3/h (the water injection amount through the core spray system is
kept at approx. 6.8m3/h). On February 12, we conducted a sampling of
gas in the gas management system in the Primary Containment Vessel of
Unit 2 and the result is that around the entry of the system, Xe-135
was below the detection limit (9.5 x 10-2 Bq/cm3). As it is below 1
Bq/cm3, the criterion to judge re-criticality, we have confirmed that
it has not reached re-criticality. Currently, the temperature is
approx.75.4°C (as of 5 am on February 12). We are now considering
change of the water injection amount.
- At 9:57 am on February 12, we started to transfer accumulated water in
the underground of turbine building of Unit 3 to the Centralized
Radiation Waste Treatment Facility (Process Main Building).
· Fukushima Daini Nuclear Power Station:
(Units 1 to 4: shutdown due to the earthquake)
· Kashiwazaki Kariwa Nuclear Power Station: Units 6: under normal operation
(Units 1 to 5 and 7: outage due to regular inspections)
[Thermal Power Station]
· Power supply has returned to normal and the facilities damaged by the
earthquake are now being handled in a timely manner.
[Hydro Power Station]
· Power supply has returned to normal and the facilities damaged by the
earthquake are now being handled in a timely manner.
[Impacts on Transmission Facilities]
· Power supply has returned to normal and the facilities damaged by the
earthquake are now being handled in a timely manner.
[Impacts on Power Supply and Demand Balance]
This winter, there are some minus factors such as the regular inspection
of Unit 5 at Kashiwazaki-Kariwa Nuclear Power Station. On the other hand,
there are several plus factors such as the recovery of the common thermal
power stations which suffered the earthquake. As a result, we expect to
secure 53.7 GW (at the end of February) supply power.
Compared to the maximum demand in the last winter, which is 51.5 GW, we
will have 2.2 GW generation reserve margin.
We expect to maintain stable power supply this winter, however, as there
remains possibilities of unplanned shutdowns at our power stations and
growth in the demand according to the rapid change in the temperature, we
would like to ask your reasonable effort to save electricity.
We will continue to make our efforts to maintain stable operation and
maintenance of the power facilities in order to "prevent in principle" the
planned blackouts and secure power supply.
Appendix: Past Progress (As of 10:00 am on February 12, 2012) (PDF 420KB)
Appendix: Past Progress (From March 11, 2011 to July 31, 2011) (PDF 225KB)
* Revised past progress