search



Corporate Information

 
Press Release (Feb 02,2012)
Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 4:00 pm, February 2)
Due to the Tohoku-Chihou-Taiheiyou-Oki Earthquake which occurred on March
11, 2011, TEPCO's facilities including our nuclear power stations have
been severely damaged. We deeply apologize for the anxiety and
inconvenience caused.
With regard to the accident at Fukushima Daiichi Nuclear Power Station, on
April 17, 2011, we have compiled the roadmap towards restoration from the
accident and on July 19 we accomplished the Step1 target "Radiation dose
is in steady decline". Then on December 16 we confirmed the accomplishment
of the Step 2 target "Release of radioactive materials is under control
and radiation doses are being significantly held down".
In addition, on December 21, 2011, we have compiled the "Mid-to-long-Term
Roadmap toward the Decommissioning of Fukushima Daiichi Nuclear Power
Units 1-4, TEPCO".
In addition to the maintenance of the plant's stable condition, we will
implement Mid-to-Long Term countermeasures towards the decommissioning of
Fukushima Daiichi Nuclear Power Units 1-4 to enable evacuees to return to
their homes as soon as possible and reduce the anxiety of the people in
Fukushima and the whole nation as soon as possible.
Below is the status of TEPCO's major facilities.
*The updates are underlined.
[Nuclear Power Station]
· Fukushima Daiichi Nuclear Power Station: Unit 1 to 3: shut down due to
  the earthquake:
  (Units 4 to 6: outage due to regular inspections before the earthquake)
- To improve reliability of water injection to a reactor, line connecting 
  to injection piping in water injection line of reactor injection pump on 
  the hill of Unit 1 had replaced with polyethylene piping. So at 10:35 am, 
  we changed injection route from injection pump in turbine building to 
  reactor injection pump on the hill.
- Due to replacement to polyethylene piping was done, the amount of water
  injected has been changed gradually. At 10:55 am in February 2, we 
  adjusted water injection volume to the reactor of Unit 2 through the 
  feed water system from approx. 3.9 m3/h to approx. 3.0 m3/h, and the 
  volume from the reactor core spray system from approx. 5.1 m3/h to 
  approx. 6.0m3/h. At 11:10 am we adjusted water injection volume to the 
  reactor of Unit 3 through the feed water system from approx. 3.8 m3/h to 
  approx. 3.0 m3/h, and the volume from the reactor core spray system from 
  approx. 5.2 m3/h to approx. 6.0m3/h.
- At 8:36 am on February 2, second Cesium adsorption apparatus was stopped
  to backwash the filter because there was a gradual downward tendency. At 
  11:12 am of the same day, we restarted the apparatus and at 11:15 am, 
  reached to steady volume of water flow (36m3/h)
- At approx. 10:30 pm on January 31, we found that the water was leaking
  from the indicator test line in the rack instruments for jet pumps were
  stored. At 10:43 pm, the leakage was stopped after the main valve
  leading to the rack was closed. Debris were scattered around on the
  floor, and the volume of leaked water was approx. 6 litters as far as we
  could confirmed. Please note that it didn't run off outside of the
  reactor building. We sampled the water in the test line and measured the
  radioactivity concentration. From the results, we estimated the water
  leaked from the reactor well (analysis result: 35.5 Bq/cm3). We 
  estimated the amount of water leaked is 8,500 litters by measuring 
  decrease in water level of skimmer surge tank
- We confirmed the decrease in volume of injecting water to reactors, so 
  at 3:15 pm on February 2, we adjusted volume of water injection in each 
  reactor as follows: 
 · Unit 1:Feed water system from approx. 4.2 m3/h to approx. 4.5 m3/h, 
   Reactor core spray system from approx. 1.5 m3/h to approx. 2.0m3/h. 
 · Unit 2:Feed water system from approx. 2.5 m3/h to approx. 3.0 m3/h, 
   Reactor core spray system from approx. 5.2 m3/h to approx. 5.5m3/h. 
 · Unit 3:Feed water system from approx. 2.5 m3/h to approx. 3.0 m3/h, 
   Reactor core spray system from approx. 5.2 m3/h to approx. 5.5m3/h.
- At 3:20 pm on February 2, a Tepco worker on patrolling at reactor 
  building of Unit 4 found the very small flow(just as much as lead in 
  pencil) of water in north west corner in first floor of the reactor 
  building. This leakage seemed to be occurred at make up water system in 
  reactor well because the valve at reactor well is closed totally and so 
  the leakage seemed not be from reactor well. We are investigating 
  further. No water leakage to out side of reactor building.
- Newly found water leakage caused by congelation after the latest report 
  (at 10:00 am February 1) are as follows: 
 · two valves in discharged water piping at water treatment building where 
   filtrate water purified(Found at 3:30 pm on February 2 ) 
 · (Filtrate water(water taken from dam): approx. 0.5 litters)
- At 10:00 am on February 2, we started transferring the water accumulated
  in the basemen of Turbine Building at Unit 6 to temporary tanks. At 4:00 
  pm of the same day, we stopped transferring.
· Fukushima Daini Nuclear Power Station:
 (Units 1 to 4: shutdown due to the earthquake)
- To switch from the temporary power board to the regular power board with 
  finishing installation of the circuit breaker supplying power for Unit 3, 
  the Fuel Pool Cooling and Filtering System was suspended from 1:36 pm to 
  2:14 pm on February 2, and the Clean Up Water System was suspended from 
  1:40 pm to 2:10 pm(Temperature of the spent fuel pool when 
  stopped:25.4°C, Temperature of the spent fuel pool when restarted:25.4°C)
· Kashiwazaki Kariwa Nuclear Power Station: Units 6: under normal
  operation
  (Units 1 to 5 and 7: outage due to regular inspections)
[Thermal Power Station] 
· Power supply has returned to normal and facilities damaged by the
  earthquake are now being handled in a timely manner.
[Hydro Power Station] 
· Power supply has returned to normal and facilities damaged by the
  earthquake are now being handled in a timely manner.
[Impacts on Transmission Facilities] 
· Power supply has returned to normal and facilities damaged by the
  earthquake are now being handled in a timely manner.
[Impacts on Power Supply and Demand Balance] 
This winter, there are some minus factors such as the regular inspection 
of Unit 5 at Kashiwazaki-Kariwa Nuclear Power Station*. On the other hand, 
there are several plus factors such as the recovery of the common thermal 
power stations which suffered the earthquake. As a result, we expect to 
secure 53.7 GW (at the end of February) supply power. 
Compared to the maximum demand in the last winter, which is 51.5 GW, we 
will have 2.2 GW generation reserve margin.
We expect to maintain stable power supply this winter, however, as there 
remains possibilities of unplanned shutdowns at our power stations and 
growth in the demand according to the rapid change in the temperature, we 
would like to ask your reasonable effort to save electricity.
We will continue to make our efforts to maintain stable operation and 
maintenance of the power facilities in order to "prevent in principle" the 
planned blackouts and secure power supply.
* Correction of Description in [Impacts on Power Supply and Demand Balance] 
We described,"there will be some minus factors such as the regular 
inspection of Unit 5 at Kashiwazaki-Kariwa Nuclear Power Station" in the 
previous press release. However, because Unit 5 of Kashiwazaki-Kariwa 
Nuclear Power Station has already conducted a regular inspection since 
January 25, we revise the previous sentence to "there are some minus 
factors such as the regular inspection of Unit 5 at Kashiwazaki-Kariwa 
Nuclear Power Station". We would like to apologize for the correction 
(February 8, 2012).

Appendix: Past Progress (As of 4:00 pm, February 2, 2012) (PDF 472KB) 
Appendix: Past Progress (From March 11, 2011 to July 31, 2011) (PDF 225KB) 

* Revised past progress 
back to page top


to TOP