Due to the Tohoku-Chihou-Taiheiyou-Oki Earthquake which occurred on March
11, 2011, TEPCO's facilities including our nuclear power stations have
been severely damaged. We deeply apologize for the anxiety and
inconvenience caused.
With regard to the accident at Fukushima Daiichi Nuclear Power Station, on
April 17, 2011, we have compiled the roadmap towards restoration from the
accident and on July 19 we accomplished the Step1 target "Radiation dose
is in steady decline". Then on December 16 we confirmed the accomplishment
of the Step 2 target "Release of radioactive materials is under control
and radiation doses are being significantly held down".
In addition, on December 21, 2011, we have compiled the "Mid-to-long-Term
Roadmap toward the Decommissioning of Fukushima Daiichi Nuclear Power
Units 1-4, TEPCO".
In addition to the maintenance of the plant's stable condition, we will
implement Mid-to-Long Term countermeasures towards the decommissioning of
Fukushima Daiichi Nuclear Power Units 1-4 to enable evacuees to return to
their homes as soon as possible and reduce the anxiety of the people in
Fukushima and the whole nation as soon as possible.
Below is the status of TEPCO's major facilities.
*The updates are underlined.
[Nuclear Power Station]
· Fukushima Daiichi Nuclear Power Station: Unit 1 to 3: shut down due to
the earthquake:
(Units 1 to 4: shutdown due to the earthquake)
- At 10:12 pm on January 28, we started transferring accumulated water
from the basement floor of the turbine building of Unit 2 to the
Centralized Radiation Waste Treatment Facility (Miscellaneous Solid
Waste Volume Reduction Treatment Building [High Temperature Incinerator
Building] and the process main building). At 8:21 am of January 29 we
have stopped this transfer.
- At 10:06 pm on January 28, we started transferring accumulated water
from the basement floor of the turbine building of Unit 3 to the
Centralized Radiation Waste Treatment Facility (Miscellaneous Solid
Waste Volume Reduction Treatment Building [High Temperature Incinerator
Building] and the process main building). At 8:18 am of January 29 we
have stopped this transfer.
- At 10:00 am on January 28, we started transferring accumulated water
from the basement floor of the turbine building of Unit 6 to the
temporary tank. At 4:00 pm of the same day we have stopped this transfer.
- At 8:49 am on January 29, since a gradual decline was confirmed in the
amount of treatment at the second Cesium adsorption apparatus (sally),
we temporarily stopped this facility in order to conduct reverse wash of
the filter.
- At 9:37 am on January 29, due to switching in the water piping system of
the reactor water injection pump on the hill, we adjusted water
injection from the feed water system to the reactor of Unit 1 from
approx. 4.5 m3/h to approx. 5.5 m3/h, and the injection from the reactor
core spray system from approx. 2.0 m3/h to 1.0m3/h.
- At 10:00 am on January 29, since we confirmed decrease in water
injection to the reactor of Unit 3 we adjusted water injection from the
reactor core spray system from approx. 1.5 m3/h to 2.0m3/h. (water
injection from the feed water system is maintained at approx. 7.1 m3/h.)
- At 9:50 am of January 29, one of our employees, during adjustment works
of the water flow to the feed water spray system, found a water leak
from near the flow rate detector of the emergency reactor injection pump
on the hill (C) which is now at standby. We shut down the valve at the
leakage point and at 9:55 am confirmed that the water leak has stopped
(amount of leakage under examination). The leakage point is on the hill
(at the front of the main office building) and there are traces that
show that a certain amount of water has flowed into the drain, and we
are examining whether this water has flowed into the ocean or not. The
surface radioactivity concentration near the leakage point is as the
same level as the atmosphere around (radioactivity concentration near
the evaporative concentration apparatus is below measurable limit in all
three major nuclides (sampled on 20 December 2011)
: I-131: 1.6X10-2Bq/cm3, Cs-134:2.9X10-2Bq/cm3, Cs-137:3.3X10-2Bq/cm3,
and 6.0X10-1Bq/cm3 for all beta nuclides (sampled on 29 November 2011)).
Water injection to the reactor is maintained by the ordinary reactor
injection pump on the hill (A) and (C).
- Around 9:35am on 29 January 2012, an alarm on a system failure (Unit 4
SFP backup cooling system) was given in Unit 4 spent fuel pool backup
cooling system. According to the site investigation, a pump (A)
to circulate cooling water of a secondary system had been stopped and
the water circulation was stopped accordingly (Fuel pool temperature at
the time of the alarm: 21°C). After the event, we discovered cooling
water leakage from A2 line of air-fin cooler unit (A1-A4 lines) of the A
system of the secondary system. We confirmed that the water leakage was
stopped by closing valve of the Unit A2 line. The cooling water is from
a filtrate tank for fire extinction and doesn't contain radioactive
materials. The stopped secondary pump (A) was restarted at 11:14am and
water cooling of the spent fuel pool was restarted accordingly (Fuel
pool temperature at the time of cooling restart: 21°C)
· Fukushima Daini Nuclear Power Station:
(Units 1 to 4: shutdown due to the earthquake)
· Kashiwazaki Kariwa Nuclear Power Station: Units 6: under normal
operation
(Units 1 to 5 and 7: outage due to regular inspections)
[Thermal Power Station]
· Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Hydro Power Station]
· Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Impacts on Transmission Facilities]
· Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Impacts on Power Supply and Demand Balance]
This winter, there are some minus factors such as the regular inspection
of Unit 5 at Kashiwazaki-Kariwa Nuclear Power Station*. On the other hand,
there are several plus factors such as the recovery of the common thermal
power stations which suffered the earthquake. As a result, we expect to
secure 54.6 GW (at the end of January), 53.7 GW (at the end of February)
supply power.
Compared to the maximum demand in the last winter, which is 51.5 GW, we
will have 2.2 - 3.1 GW generation reserve margin.
We expect to maintain stable power supply this winter, however, as there
remains possibilities of unplanned shutdowns at our power stations and
growth in the demand according to the rapid change in the temperature, we
would like to ask your reasonable effort to save electricity.
We will continue to make our efforts to maintain stable operation and
maintenance of the power facilities in order to "prevent in principle"
the planned blackouts and secure power supply.
* Correction of Description in [Impacts on Power Supply and Demand Balance]
We described,"there will be some minus factors such as the regular
inspection of Unit 5 at Kashiwazaki-Kariwa Nuclear Power Station" in the
previous press release. However, because Unit 5 of Kashiwazaki-Kariwa
Nuclear Power Station has already conducted a regular inspection since
January 25, we revise the previous sentence to "there are some minus
factors such as the regular inspection of Unit 5 at Kashiwazaki-Kariwa
Nuclear Power Station". We would like to apologize for the correction
(February 8, 2012).
Appendix: Past Progress (As of 11:30 am, January 29, 2012) (PDF 376KB)
Appendix: Past Progress (From March 11, 2011 to July 31, 2011) (PDF 225KB)
* Revised past progress