Due to the Tohoku-Chihou-Taiheiyou-Oki Earthquake which occurred on March
11, 2011, TEPCO's facilities including our nuclear power stations have
been severely damaged. We deeply apologize for the anxiety and
inconvenience caused.
With regard to the accident at Fukushima Daiichi Nuclear Power Station, on
April 17, 2011, we have compiled the roadmap towards restoration from the
accident and on July 19 we accomplished the Step1 target "Radiation dose
is in steady decline". Then on December 16 we confirmed the accomplishment
of the Step 2 target "Release of radioactive materials is under control
and radiation doses are being significantly held down".
In addition, on December 21, 2011, we have compiled the "Mid-to-long-Term
Roadmap toward the Decommissioning of Fukushima Daiichi Nuclear Power
Units 1-4, TEPCO".
In addition to the maintenance of the plant's stable condition, we will
implement Mid-to-Long Term countermeasures towards the decommissioning of
Fukushima Daiichi Nuclear Power Units 1-4 to enable evacuees to return to
their homes as soon as possible and reduce the anxiety of the people in
Fukushima and the whole nation as soon as possible.
Below is the status of TEPCO's major facilities.
* The updates are underlined.
[Nuclear Power Station]
· Fukushima Daiichi Nuclear Power Station: Unit 1 to 3: shut down due to
the earthquake:
(Units 1 to 4: shutdown due to the earthquake)
- For the reliability enhancement of water injection into the reactor, the
water discharge line of the reactor water injection pump on the hill is
planned to be changed from pressure hose to polyethylene pipe. Therefore,
there is the necessity of the temporary stopping of water injection from
the reactor water injection pump for it. At 11:50 am January 26, the
water injection to the reactor of Unit 3 from the feed water injection
system was switched from the reactor water injection pump to the reactor
water injection pump in the turbine building. At 9:14 am on January 27,
the volume from the feed water system increased from approx. 8.5 m3/h to
approx. 8.9 m3/h, and the volume from the reactor core spray system
decreased from approx. 1.0 m3/h to 0 m3/h. because the replacing work of
the water injection line of the reactor water injection pump on the hill
was finished at 2:49 pm, regarding the water injection from the feed
water system, we switched the pump from in the turbine building to on
the hill at 3:01pm. At 3:11 pm, the volume from the feed water system
decreased from approx. 8.9 m3/h to approx. 7.9 m3/h, and the volume from
reactor core spray system increased from 0 m3/h to 1.0 m3/h.
- At around 11:20 on January 27, the subcontractor employees who were
patrolling at that time found the leakage at the flange of the pure
water piping between the Solid Waste Storage and the Regular Inspection
Material Storage, which is approx. 0.5 liter/min. At around 1:28 pm,
After retightening, we confirmed that the leakage stopped. In addition,
the leakage water was pure water (The radiation dose in ambient air near
the leaking point was not different from surrounding area). Because
there was no drain around there, it is considered that there was no
leakage to the ocean.
· Fukushima Daini Nuclear Power Station:
(Units 1 to 4: shutdown due to the earthquake)
· Kashiwazaki Kariwa Nuclear Power Station: Units 6: under normal
operation
(Units 1 to 5 and 7: outage due to regular inspections)
[Thermal Power Station]
· Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Hydro Power Station]
· Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Impacts on Transmission Facilities]
· Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Impacts on Power Supply and Demand Balance]
This winter, there are some minus factors such as the regular inspection
of Unit 5 at Kashiwazaki-Kariwa Nuclear Power Station*. On the other hand,
there are several plus factors such as the recovery of the common thermal
power stations which suffered the earthquake. As a result, we expect to
secure 54.6 GW (at the end of January), 53.7 GW (at the end of February)
supply power.
Compared to the maximum demand in the last winter, which is 51.5 GW, we
will have 2.2 - 3.1 GW generation reserve margin.
We expect to maintain stable power supply this winter, however, as there
remains possibilities of unplanned shutdowns at our power stations and
growth in the demand according to the rapid change in the temperature, we
would like to ask your reasonable effort to save electricity.
We will continue to make our efforts to maintain stable operation and
maintenance of the power facilities in order to "prevent in principle" the
planned blackouts and secure power supply.
* Correction of Description in [Impacts on Power Supply and Demand Balance]
We described,"there will be some minus factors such as the regular
inspection of Unit 5 at Kashiwazaki-Kariwa Nuclear Power Station" in the
previous press release. However, because Unit 5 of Kashiwazaki-Kariwa
Nuclear Power Station has already conducted a regular inspection since
January 25, we revise the previous sentence to "there are some minus
factors such as the regular inspection of Unit 5 at Kashiwazaki-Kariwa
Nuclear Power Station". We would like to apologize for the correction
(February 8, 2012).
Appendix: Past Progress (As of 3:30 pm, January 27, 2012) (PDF 367KB)
Appendix: Past Progress (From March 11, 2011 to July 31, 2011) (PDF 225KB)
* Revised past progress