Press Release (Jan 16,2012)
Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 10:00 am, January 16)
Due to the Tohoku-Chihou-Taiheiyou-Oki Earthquake which occurred on March 
11, 2011, TEPCO's facilities including our nuclear power stations have been 
severely damaged. We deeply apologize for the anxiety and inconvenience 
caused.
With regard to the accident at Fukushima Daiichi Nuclear Power Station, on 
April 17, 2011, we have compiled the roadmap towards restoration from the 
accident and on July 19 we accomplished the Step1 target "Radiation dose 
is in steady decline". Then on December 16 we confirmed the accomplishment 
of the Step 2 target "Release of radioactive materials is under control 
and radiation doses are being significantly held down".
In addition, on December 21, 2011, we have compiled the "Mid-to-long-Term 
Roadmap toward the Decommissioning of Fukushima Daiichi Nuclear Power Units 
1-4, TEPCO".
In addition to the maintenance of the plant's stable condition, we will 
implement Mid-to-Long Term countermeasures towards the decommissioning of 
Fukushima Daiichi Nuclear Power Units 1-4 to enable evacuees to return to 
their homes as soon as possible and reduce the anxiety of the people in 
Fukushima and the whole nation as soon as possible.

Below is the status of TEPCO's major facilities.

* Updates since the previous press release underlined.
[Nuclear Power Station] 
· Fukushima Daiichi Nuclear Power Station: Unit 1 to 3: shut down due to 
  the earthquake 
    (Units 4 to 6: outage due to regular inspections) 

  - At 5:26 pm on January 15, the decrease of injection water flow to 
    Reactor was found so that water injection from Core Spray System was 
    adjusted from approx. 1.8 m3/h to 2.0 m3/h (water injection from feed 
    water system was remained unchanged as approx. 4.5 m3/h).  
  - At 9:13 am on January 16, we suspended the second cesium absorption 
    apparatus due to reverse cleaning of the filters because the amount of 
    disposal water of the second cesium absorption apparatus decreased 
    gradually. 
  - At 10:00 am on January 16, we started the transferring of accumulated 
    water at the underground of Unit 6 turbine building to temporary tank. 

· Fukushima Daini Nuclear Power Station:
    (Units 1 to 4: shutdown due to the earthquake)

· Kashiwazaki Kariwa Nuclear Power Station: Units 5, 6: under normal 
  operation
    (Units 1 to 4 and 7: outage due to regular inspections)
[Thermal Power Station] 
· Power supply has returned to normal and facilities damaged by the  
  earthquake are now being handled in a timely manner.
[Hydro Power Station] 
· Power supply has returned to normal and facilities damaged by the  
  earthquake are now being handled in a timely manner.
[Impacts on Transmission Facilities] 
· Power supply has returned to normal and facilities damaged by the  
  earthquake are now being handled in a timely manner.
[Impacts on Power Supply and Demand Balance] 
This winter, there will be some minus factors such as the regular  
inspection of Unit 5 at Kashiwazaki-Kariwa Nuclear Power Station. On the 
other hand, there will be several plus factors such as the recovery of the 
common thermal power stations which suffered the earthquake. As a result, 
we expect to secure 54.6 GW (at the end of January), 53.7 GW (at the end 
of February) supply power. 
Compared to the maximum demand in the last winter, which is 51.5 GW, we  
will have 2.2 - 3.1 GW generation reserve margin. 

We expect to maintain stable power supply this winter, however, as there  
remains possibilities of unplanned shutdowns at our power stations and 
growth in the demand according to the rapid change in the temperature, we 
would like to ask your reasonable effort to save electricity. 

We will continue to make our efforts to maintain stable operation and 
maintenance of the power facilities in order to "prevent in principle" the 
planned blackouts and secure power supply. 
Appendix: Past Progress (As of 10:00 am, January 16, 2012) (PDF 331KB) 
Appendix: Past Progress (From March 11, 2011 to July 31, 2011) (PDF 225KB) 

* Revised past progress 