Due to the Tohoku-Chihou-Taiheiyou-Oki Earthquake which occurred on March
11, 2011, TEPCO's facilities including our nuclear power stations have
been severely damaged. We deeply apologize for the anxiety and
inconvenience caused.
With regard to the accident at Fukushima Daiichi Nuclear Power Station, on
April 17, 2011, we have compiled the roadmap towards restoration from the
accident and on July 19 we accomplished the Step1 target "Radiation dose
is in steady decline". Then on December 16 we confirmed the accomplishment
of the Step 2 target "Release of radioactive materials is under control
and radiation doses are being significantly held down".
In addition, on December 21, 2011, we have compiled the "Mid-to-long-Term
Roadmap toward the Decommissioning of Fukushima Daiichi Nuclear Power
Units 1-4, TEPCO".
In addition to the maintenance of the plant's stable condition, we will
implement Mid-to-Long Term countermeasures towards the decommissioning of
Fukushima Daiichi Nuclear Power Units 1-4 to enable evacuees to return to
their homes as soon as possible and reduce the anxiety of the people in
Fukushima and the whole nation as soon as possible.
Below is the status of TEPCO's major facilities.
* Updates since the previous press release underlined.
[Nuclear Power Station]
・ Fukushima Daiichi Nuclear Power Station: Unit 1 to 3: shut down due to
the earthquake
(Units 4 to 6: outage due to regular inspections)
* At 10:00 am on January 4 2012, we started transferring accumulated
water from the basement of the turbine building of Unit 6 to the
temporary tank. At 4:00 pm on the same day we stopped this.
* On January 4 2012, we conducted sampling of the gas of the PCV gas
management system of the primary containment vessel of units 1 and 2.
As a result of the analysis, we confirmed that at the entrance of the
system Xenon 135 was below detection limit (Unit 1 : 1.1 x 10-1Bq/cm3,
Unit 2 : 1.0 x 10-1Bq/cm3), and below the re-criticality criterion
which is 1Bq/cc.
* Since December 22, 2011, the atmospheric temperatures at point C of
Unit 1 Primary Containment Vessel (PCV) monitored by the Containment
Atmospheric Monitoring System had risen (the atmospheric temperature of
the PCV on December 22 was approx. 38°C, at 7 pm on December 27 was
approx. 49°C). The other temperatures had not risen, so we conducted a
survey checking the reliability of the meters from 9 am to 10 am on
December 28, and we confirmed that there are no problems. From 11:00am
to 12:15pm on the same day, we adjusted the volume of Nitrogen
injection, from approx. 8 m3/h to approx.18 m3/h, and emission of the
gas management system, from approx. 23 m3/h to approx.30 m3/h, in order
to identify the cause by monitoring the system with the same injection
and emission volume as before December 22. The temperature went up to
approx. 54.6°C at 6 pm on December 28 and fell to approx. 41.6°C at
5:00 am on January 5, 2012. Temperatures at other two points also
indicated slight increases but are currently in the stable status.
Point D: (Maximum) approx. 35.8°C at 5:00 pm on December 29, 2011 →
approx. 31.4°C at 5:00 am on January 5, 2012.
Point E: (Maximum) approx. 40.0°C at 5:00 pm on December 29, 2011 →
approx. 34.4°C at 5:00 am on January 5, 2012.
We will continuously conduct the survey for the cause of temperature
increase and surveillance of the plant.
* At 9:30 am on January 5 2012, we started transferring accumulated water
from the ground floor of the turbine building of Unit 2 to the
Centralized Radiation Waste Treatment Facility (Miscellaneous Solid
Waste Volume Reduction Treatment Building [High Temperature Incinerator
Building] and the Process Main Building) .
* At 9:58 am on 5 January 2012, due to diversification works of reactor
water injection pumps, we adjusted water injection through reactor feed
water system from approx.1.7m3/h to 1m3/h, and water injection from
core spray system from approx. 8.2m3/h to 9m3/h.
・ Fukushima Daini Nuclear Power Station:
Units 1 to 4: shutdown due to the earthquake
・ Kashiwazaki Kariwa Nuclear Power Station: Units 5, 6: under normal
operation
(Units 1 to 4 and 7: outage due to regular inspections)
[Thermal Power Station]
・ Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Hydro Power Station]
・ Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Impacts on Transmission Facilities]
・ Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Impacts on Power Supply and Demand Balance]
This winter, there will be some minus factors such as the regular
inspection of Unit 5 at Kashiwazaki-Kariwa Nuclear Power Station. On the
other hand, there will be several plus factors such as the recovery of the
common thermal power stations which suffered the earthquake. As a result,
we expect to secure 54.9 GW (at the end of December), 54.6 GW (at the end
of January), 53.7 GW (at the end of February) supply power.
Compared to the maximum demand in the last winter, which is 51.5 GW, we
will have 2.2 - 3.4 GW generation reserve margin.
We expect to maintain stable power supply this winter, however, as there
remains possibilities of unplanned shutdowns at our power stations and
growth in the demand according to the rapid change in the temperature, we
would like to ask your reasonable effort to save electricity.
We will continue to make our efforts to maintain stable operation and
maintenance of the power facilities in order to "prevent in principle" the
planned blackouts and secure power supply.
Appendix: Past Progress (As of 10:00 am, January 5, 2012) (PDF 458KB)
Appendix: Past Progress (From March 11, 2011 to July 31, 2011) (PDF 225KB)
* Revised past progress