Due to the Tohoku-Chihou-Taiheiyou-Oki Earthquake which occurred on March
11, 2011, TEPCO's facilities including our nuclear power stations have
been severely damaged. We deeply apologize for the anxiety and
inconvenience caused.
With regard to the accident at Fukushima Daiichi Nuclear Power Station, on
April 17, we have compiled the roadmap towards restoration from the
accident and on July 19 we accomplished the Step1 target "Radiation dose
is in steady decline". Then on December 16 we confirmed the accomplishment
of the Step 2 target "Release of radioactive materials is under control
and radiation doses are being significantly held down".
In addition, on December 21, we have compiled the "Mid-to-long-Term
Roadmap toward the Decommissioning of Fukushima Daiichi Nuclear Power
Units 1-4, TEPCO".
In addition to the maintenance of the plant's stable condition, we will
implement Mid-to-Long Term countermeasures towards the decommissioning of
Fukushima Daiichi Nuclear Power Units 1-4 to enable evacuees to return to
their homes as soon as possible and reduce the anxiety of the people in
Fukushima and the whole nation as soon as possible.
Below is the status of TEPCO's major facilities.
*Updates since the previous press release underlined.
[Nuclear Power Station]
·Fukushima Daiichi Nuclear Power Station: Unit 1 to 3: shut down due to
the earthquake
(Units 4 to 6: outage due to regular inspections)
*Accumulated water in the trench located between the process main building
of Centralized Radiation Waste Treatment Facility and Miscellaneous Solid
Waste Volume Reduction Treatment Building (High Temperature Incinerator
Building) found on December 18 was started to transfer to Miscellaneous
Solid Waste Volume Reduction Treatment Building (High Temperature
Incinerator Building) from 10:19 am on December 23. At 8:13 pm on the
same day, the water transfer was stopped because the planed transfer was
completed (transfer volume: about 120 m3). The volume of accumulated
water was estimated at about 230 m3 from general drawings. However, after
confirmation of the structure of the trench in detail, it was estimated
at about 220 m3. In this context, the remaining accumulated water was
estimated at about 100 m3. A method to transfer the remaining water will
be planned from now.
*At 4:07 pm on December 23, we started to transfer accumulated water from
the basement of turbine building of Unit 1 to the basement of turbine
building of Unit 2.
·Fukushima Daini Nuclear Power Station:
Units 1 to 4: shutdown due to the earthquake
·Kashiwazaki Kariwa Nuclear Power Station: Units 5, 6: under normal
operation
(Units 1 to 4 and 7: outage due to regular inspections)
[Thermal Power Station]
·Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Hydro Power Station]
·Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Impacts on Transmission Facilities]
·Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Impacts on Power Supply and Demand Balance]
This winter, there will be some minus factors such as the regular
inspection of Unit 5 at Kashiwazaki-Kariwa Nuclear Power Station. On the
other hand, there will be several plus factors such as the recovery of the
common thermal power stations which suffered the earthquake. As a result,
we expect to secure 54.9 GW (at the end of December), 54.6 GW (at the end
of January), 53.7 GW (at the end of February) supply power.
Compared to the maximum demand in the last winter, which is 51.5 GW, we
will have 2.2 - 3.4 GW generation reserve margin.
We expect to maintain stable power supply this winter, however, as there
remains possibilities of unplanned shutdowns at our power stations and
growth in the demand according to the rapid change in the temperature, we
would like to ask your reasonable effort to save electricity.
We will continue to make our efforts to maintain stable operation and
maintenance of the power facilities in order to "prevent in principle" the
planned blackouts and secure power supply.
Appendix: Past Progress (As of 9:00 am, December 24, 2011) (PDF 248KB)
Appendix: Past Progress (From March 11, 2011 to July 31, 2011) (PDF 225KB)
* Revised past progress