Due to the Tohoku-Chihou-Taiheiyou-Oki Earthquake which occurred on March
11, 2011, TEPCO's facilities including our nuclear power stations have been
severely damaged. We deeply apologize for the anxiety and inconvenience
caused.
With regard to the accident at Fukushima Daiichi Nuclear Power Station, on
April 17, we have compiled the roadmap towards restoration from the
accident and on July 19 we accomplished the Step1 target "Radiation dose is
in steady decline". Then on December 16 we confirmed the accomplishment of
the Step 2 target "Release of radioactive materials is under control and
radiation doses are being significantly held down".
In addition, on December 21, we have compiled the "Mid-and-long-Term
Roadmap toward the Decommissioning of Fukushima Daiichi Nuclear Power Units
1-4, TEPCO".
In addition to the maintenance of the plant's stable condition, we will
implement Mid-to-Long Term countermeasures towards the decommissioning of
Fukushima Daiichi Nuclear Power Units 1-4 to enable evacuees to return to
their homes as soon as possible and reduce the anxiety of the people in
Fukushima and the whole nation as soon as possible.
Below is the status of TEPCO's major facilities.
* Updates since the previous press release underlined.
[Nuclear Power Station]
· Fukushima Daiichi Nuclear Power Station: Unit 1 to 3: shut down due to the
earthquake
(Units 4 to 6: outage due to regular inspections)
* At 1:30 pm on December 22, we started to inject hydrazine into Unit 3
spent fuel pool using circulating cooling system. At 3:15 pm on the same
day, the hydrazine injection was completed.
* On December 22, we conducted the gas sampling of Unit 2 Primary
Containment Vessel (PCV) Gas Control System. As a result of analysis, it
was confirmed that the gas concentration of Xe-135 at the inlet of the
PCV Gas Control System was below detective limit (1.0 x 10-1 Bq/cm2) and
lower than the standard of recriticality, 1 Bq/cc.
* At around 1 pm on December 22, it was found that the hose of Unit 3
Reactor Water Injection Line was swollen to the extent of 2 meter long.
Although there was no leakage from the swollen hose, it was decided that
the pump for Reactor water injection should be switched from the reactor
injection pump on the hill to the emergency motor pump and the hose
should be replaced with new one.(+) At 7:12 pm on the same day, the
emergency motor pump was started to operate. From 7:44 pm, the valve to
the normal water injection line was closed in order to weep drain from
the line. After the replacement of the hose, at 8:47 pm, the valve to the
normal water injection line was opened to fill water in the line. At 10
pm, it was confirmed that there was no water leakage from the new hose,
so that water injection to the Reactor was adjusted to about 3 m3/hour
from Reactor Feed Water System and about 6 m3/hour from Reactor Core
Spray System at about 10:30 pm. At 10:38 pm, the emergency motor pump was
stopped. After that, it was checked that there was no leakage from the
hose and its connection. During the hose replacement work, the water
injection was continued and there was no remarkable change in temperature
of the Reactor Pressure Vessel.
· Fukushima Daini Nuclear Power Station:
Units 1 to 4: shutdown due to the earthquake
· Kashiwazaki Kariwa Nuclear Power Station: Units 5, 6: under normal
operation
(Units 1 to 4 and 7: outage due to regular inspections)
[Thermal Power Station]
· Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Hydro Power Station]
· Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Impacts on Transmission Facilities]
· Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Impacts on Power Supply and Demand Balance]
This winter, there will be some minus factors such as the regular
inspection of Unit 5 at Kashiwazaki-Kariwa Nuclear Power Station. On the
other hand, there will be several plus factors such as the recovery of the
common thermal power stations which suffered the earthquake. As a result,
we expect to secure 54.9 GW (at the end of December), 54.6 GW (at the end
of January), 53.7 GW (at the end of February) supply power.
Compared to the maximum demand in the last winter, which is 51.5 GW, we
will have 2.2 - 3.4 GW generation reserve margin.
We expect to maintain stable power supply this winter, however, as there
remains possibilities of unplanned shutdowns at our power stations and
growth in the demand according to the rapid change in the temperature, we
would like to ask your reasonable effort to save electricity.
We will continue to make our efforts to maintain stable operation and
maintenance of the power facilities in order to "prevent in principle" the
planned blackouts and secure power supply.
+ Article 12 of Safety Regulation at Nuclear Facilities stipulates
"operational limit" and "required measures if the operational limit is
not satisfied" according to the facility management based on "the mid-
term view point for securing safety". It also stipulates to respond based
on the required measures if the operational limits is not satisfied. In
the case of today's hose swollen, it was regarded to be sifted off the
operational limit as planned (from 6:35 pm on December 22 to 10:43 pm on
the same day) from the proactive maintenance point of view, so that the
hose replacement work was implemented accordingly.
Appendix: Past Progress (As of 9:00 am, December 23, 2011) (PDF 246KB)
Appendix: Past Progress (From March 11, 2011 to July 31, 2011) (PDF 225KB)
* Revised past progress