Due to the Tohoku-Chihou-Taiheiyou-Oki Earthquake which occurred on March
11, 2011, TEPCO's facilities including our nuclear power stations have been
severely damaged. We deeply apologize for the anxiety and inconvenience
caused.
With regard to the accident at Fukushima Daiichi Nuclear Power Station, on
April 17, we have compiled the roadmap towards restoration from the
accident and on July 19 we accomplished the Step1 target "Radiation dose is
in steady decline". Then on December 16 we confirmed the accomplishment of
the Step 2 target "Release of radioactive materials is under control and
radiation doses are being significantly held down".
By bringing the reactors and spent fuel pools to a stable cooling condition
and mitigating the release of radioactive materials, we will make every
effort to enable evacuees to return to their homes and for all citizens to
be able to secure a sound life.
Below is the status of TEPCO's major facilities.
* Updates since the previous press release underlined.
[Nuclear Power Station]
· Fukushima Daiichi Nuclear Power Station: Unit 1 to 3: shut down due to the
earthquake
(Units 4 to 6: outage due to regular inspections)
* At 11:28 am on December 21, trial operation was conducted for Unit 5
residual heat removal system pump (A) which has been stopped due to the
tsunami on March 11. Because its soundness was confirmed, it was resumed
to be on stand-by at 12:49 pm. Reactor cooling was temporarily suspended
while switching pumps in trial operation, but there is no problem
regarding the cooling.
* At 1:57 pm on December 21, transfer of accumulated water was started from
Unit 2 turbine building to the Centralized Radiation Waste Treatment
Facility (Miscellaneous Solid Waste Volume Reduction Treatment Building
[High temperature incinerator building] and Process Main Building).
* On December 21, regarding nitrogen injection to the PCV and gas exhaust
amount from the PCV gas controlling system, change in nitrogen injection
amount and gas exhaust amount from the gas controlling system was
conducted based on the past operation. At 2:52 pm on the same day,
injection of nitrogen to the PCV was adjusted from approx. 16 m3/h to
approx. 10 m3/h. At 3:15 pm. A gas exhaust amount from gas controlling
system was adjusted from approx. 40 m3/h to approx. 32 m3/h.
· Fukushima Daini Nuclear Power Station:
Units 1 to 4: shutdown due to the earthquake
* At 10:15 am on 29th August, in order to investigate soundness of reactor
containment vessel of unit 4 and inside facilities, we have opened
airlock for site workers (hatch to enter into the primary containment
vessel), and we started investigation. On September 7, we implemented the
cleaning and decontamination. Since November 21, we had been conducted
the visual inspection of the reactor containment vessel and inside
facilities and finished the inspection today. In the result, there were
no reactor coolant leakages and no damages of facilities, equipments and
pipes. Therefore, we have confirmed that there are no harmful effects for
cold shutdown. Although there were some removal of paints of equipments
due to high temperature and humidity, we estimated it has no direct
impact on the cold shutdown. We will conduct detail inspection of the
reactor containment vessel including inside facilities.
· Kashiwazaki Kariwa Nuclear Power Station: Units 5, 6: under normal
operation
(Units 1 to 4 and 7: outage due to regular inspections)
[Thermal Power Station]
· Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Hydro Power Station]
· Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Impacts on Transmission Facilities]
· Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Impacts on Power Supply and Demand Balance]
This winter, there will be some minus factors such as the regular
inspection of Unit 5 at Kashiwazaki-Kariwa Nuclear Power Station. On the
other hand, there will be several plus factors such as the recovery of the
common thermal power stations which suffered the earthquake. As a result,
we expect to secure 54.9 GW (at the end of December), 54.6 GW (at the end
of January), 53.7 GW (at the end of February) supply power.
Compared to the maximum demand in the last winter, which is 51.5 GW, we
will have 2.2 - 3.4 GW generation reserve margin.
We expect to maintain stable power supply this winter, however, as there
remains possibilities of unplanned shutdowns at our power stations and
growth in the demand according to the rapid change in the temperature, we
would like to ask your reasonable effort to save electricity.
We will continue to make our efforts to maintain stable operation and
maintenance of the power facilities in order to "prevent in principle" the
planned blackouts and secure power supply.
Appendix: Past Progress (As of 3:30 am, December 21, 2011) (PDF 427KB)
Appendix: Past Progress (From March 11, 2011 to July 31, 2011) (PDF 225KB)
* Revised past progress