Due to the Tohoku-Chihou-Taiheiyou-Oki Earthquake which occurred on March
11, 2011, TEPCO's facilities including our nuclear power stations have
been severely damaged. We deeply apologize for the anxiety and
inconvenience caused.
With regard to the accident at Fukushima Daiichi Nuclear Power Station, on
April 17, we have compiled the roadmap towards restoration from the
accident and then we updated the progress status of roadmap considering
the current situation, on July 19. Accomplishment of the Step1 target
"Radiation dose is in steady decline" has been confirmed. On November 17,
we updated the further progress.
By bringing the reactors and spent fuel pools to a stable cooling
condition and mitigating the release of radioactive materials, we will
make every effort to enable evacuees to return to their homes and for all
citizens to be able to secure a sound life.
Below is the status of TEPCO's major facilities.
* Updates since the previous press release underlined.
[Nuclear Power Station]
· Fukushima Daiichi Nuclear Power Station: Unit 1 to 3: shut down due to
the earthquake
(Units 4 to 6: outage due to regular inspections)
* At 10:00 am on December 12, we started to transfer the water accumulated
in the basement of Unit 6 Turbine Building to the temporary tank. At
4:00 pm on the same day, we stopped the transfer.
* At 3:53 pm on December 12, the annunciator alerted for the Unit 2 SFP
alternative cooling system, which showed the difference between inlet
and outlet flow at the primary pump exceeded the limit. Any
abnormalities like water leakage were not observed by patrolling at the
site. Currently the automatic trip system by the annunciator is
temporarily removed, and monitoring the level of the skimmer surge tank
is enhanced as the alternative monitoring measure. The cooling system
will be manually tripped if there are abnormalities on the skimmer surge
tank level, which is confirmed there is no change on the level. At 5:18
pm, after vibrated the instrument piping, it was confirmed the
annunciator was cleared. It is planned to enhance the monitoring after
the inspection of flow meters and the flushing of detection lines. There
is no problem on the SFP cooling as the alternative cooling system is
continuously operated.
* On December 4, it was found that puddle water inside the barrier around
the evaporative condensation apparatus 3A to 3C was leaked through the
crack at the concrete floor widened by the deformation of the sealing
material. Afterwards the similar places were inspected, and then the
damage of the concrete floor was found around the evaporative
condensation apparatus 1A to 1C. On December 6, the repair work of the
concrete floor was completed. The leak water detection device will be
installed inside the barrier by December 15 as one of the measures for
preventing the recurrence of such leakage, in addition to the patrolling
six times a day until the device will be installed. Upon the preventing
measures are prepared, and considering the water mass balance, the
evaporative condensation apparatuses 1B, 1C and 1A were re-started on
2:33 pm, 2:46 pm and 3:50 pm on December 12, respectively.
* At around 4 pm on December 12, it was found the water spilled from the
bucket, which was used to collect drain water from sampling line of the
evaporative condensation apparatus 3C. The paddle water was spread
around 1 meter radius from the bucket (the capacity of the bucket:
approx. 7 liters, spilled water: approx. 3 liters), which stayed inside
the barrier. At around 7:30 pm, when replaced the bucket to new one, it
was confirmed that there was no leakage form the valve of the sampling
line. At around 8:30 pm, when patrolling at the site, it was found that
the water spilled from the bucket again. The paddle water was then
spread around 1.5 meter radius (the capacity of the second bucket:
approx. 12 liters, spilled water: 7 liters), which stayed inside the
barrier, too. At around 8:50 pm, the valve of the sampling line was
tightly closed as it was found that the valve was not completely closed,
and it was confirmed there was no water leakage. Around 10:25 pm, the
inlet and outlet valve of the pump was closed for pre-caution. The same
operation was done for 3A and 3B of the evaporative condensation
apparatuses. At around 11:40 pm, it was confirmed that there was no
additional leakage at the site.
* At 6:03 pm on November 30, we started the transfer of the accumulated
water from the basement of Turbine Building of Unit 2 to the centralized
radiation waste treatment facility (miscellaneous solid waste Volume
reduction treatment building [high temperature incinerator building]).
At 7:51 am on December 13, we stopped the transfer of the accumulated
water from the basement of Turbine Building of Unit 2 to the centralized
radiation waste treatment facility (miscellaneous solid waste Volume
reduction treatment building [high temperature incinerator building]) in
order to stop power supply to Unit 2 accumulated water transfer pump for
power supply enhancing work. With the stoppage of the water transfer,
the 2nd Cesium adsorption apparatus was shutdowned for replacing vessels
at 8:44 am on December 12, and will be kept outage until December 14 in
order to adjust the water level of the centralized radiation waste
treatment facility (miscellaneous solid waste Volume reduction treatment
building [high temperature incinerator building]). The Cesium adsorption
apparatus is continued its operation. Water injection to the Reactors
will not be affected since the cooling is continued by using processed
water in the buffer tank.
* With switching the power source for the improvement work of the on-site
power source, at 10:30 am on December 11, Unit 1 SFP alternative cooling
system was stopped (SFP water temperature at the time of stoppage was 14
°C). At 5:07 pm on December 12, Unit 1 SFP alternative cooling system
was resumed (SFP water temperature at the time of resume was 15 °C).
· Fukushima Daini Nuclear Power Station:
Units 1 to 4: shutdown due to the earthquake
· Kashiwazaki Kariwa Nuclear Power Station: Units 5, 6: under normal
operation
(Units 1 to 4 and 7: outage due to regular inspections)
[Thermal Power Station]
· Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Hydro Power Station]
· Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Impacts on Transmission Facilities]
· Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Impacts on Power Supply and Demand Balance]
This winter, there will be some minus factors such as the regular
inspection of Unit 5 at Kashiwazaki-Kariwa Nuclear Power Station. On the
other hand, there will be several plus factors such as the recovery of the
common thermal power stations which suffered the earthquake. As a result,
we expect to secure 54.9 GW (at the end of December), 54.6 GW (at the end
of January), 53.7 GW (at the end of February) supply power.
Compared to the maximum demand in the last winter, which is 51.5 GW, we
will have 2.2 - 3.4 GW generation reserve margin.
We expect to maintain stable power supply this winter, however, as there
remains possibilities of unplanned shutdowns at our power stations and
growth in the demand according to the rapid change in the temperature, we
would like to ask your reasonable effort to save electricity.
We will continue to make our efforts to maintain stable operation and
maintenance of the power facilities in order to "prevent in principle" the
planned blackouts and secure power supply.
Appendix: Past Progress (As of 9:00 am, December 13, 2011) (PDF 399KB)
Appendix: Past Progress (From March 11, 2011 to July 31, 2011) (PDF 225KB)
* Revised past progress