Due to the Tohoku-Chihou-Taiheiyou-Oki Earthquake which occurred on March
11, 2011, TEPCO's facilities including our nuclear power stations have been
severely damaged. We deeply apologize for the anxiety and inconvenience
caused.
With regard to the accident at Fukushima Daiichi Nuclear Power Station, on
April 17, we have compiled the roadmap towards restoration from the
accident and then we updated the progress status of roadmap considering
the current situation, on July 19. Accomplishment of the Step1 target
"Radiation dose is in steady decline" has been confirmed. On November 17,
we updated the further progress.
By bringing the reactors and spent fuel pools to a stable cooling condition
and mitigating the release of radioactive materials, we will make every
effort to enable evacuees to return to their homes and for all citizens to
be able to secure a sound life.
Below is the status of TEPCO's major facilities.
* Underlined are updates from the previous press release.
[Nuclear Power Station]
· Fukushima Daiichi Nuclear Power Station: Unit 1 to 3: shut down due to
the earthquake
(Units 4 to 6: outage due to regular inspections)
* At 1:26 pm on November 30, we started injection of hydrazine into spent
fuel pool of unit 2 by using
circulating cooling system and stopped such injection at 3:04 pm on
the same day.
* At 4:04 pm on November 30, we started operation to inject nitrogen into
the reactor pressure vessel. At 4:08 pm, injection amount reached the
scheduled amount of 5 m3/h. At 4:26 pm, we started operation to inject
nitrogen into the reactor pressure vessel. At 4:40 pm, injection amount
reached the scheduled amount of 5 m3/h.
* At 6:03 pm on November 30, we started transfer of the accumulated water
from the basement of Unit 2 turbine building to Centralized Radiation
Waste Treatment Facility (Miscellaneous Solid Waste Volume Reduction
Treatment Building [High Temperature Incinerator Building]).
* At 11:13 on November 30, the alarm went off at the alternative cooling
system in the Fuel Pool Cooling and Filtering System indicating that
the difference of the flow rate between at the inlet and at the outlet
is large and the system automatically stopped its operation. At 11:34
pm on the same day, no leakage was confirmed by the site inspection.
At 11:00 pm on the same day, the temperature of spent fuel pool was
22.7 °C and the anticipated temperature increase was 0.3 °C/h. As
there is sufficient buffer, the inspection is scheduled during the
morning of December 1.
· Fukushima Daini Nuclear Power Station:
Units 1 to 4: shutdown due to the earthquake
· Kashiwazaki Kariwa Nuclear Power Station: Units 5, 6: under normal
operation
(Units 1 to 4 and 7: outage due to regular inspections)
[Thermal Power Station]
- Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Hydro Power Station]
- Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Impacts on Transmission Facilities]
- Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Impacts on Power Supply and Demand Balance]
This winter, there will be some minus factors such as the regular
inspection of Unit 5 at Kashiwazaki-Kariwa Nuclear Power Station. On the
other hand, there will be several plus factors such as the recovery of the
common thermal power stations which suffered the earthquake. As a result,
we expect to secure 54.9 GW (at the end of December), 54.6 GW (at the end
of January), 53.7 GW (at the end of February) supply power.
Compared to the maximum demand in the last winter, which is 51.5 GW, we
will have 2.2 - 3.4 GW generation reserve margin.
We expect to maintain stable power supply this winter, however, as there
remains possibilities of unplanned shutdowns at our power stations and
growth in the demand according to the rapid change in the temperature, we
would like to ask your reasonable effort to save electricity.
We will continue to make our efforts to maintain stable operation and
maintenance of the power facilities in order to "prevent in principle"
the planned blackouts and secure power supply.
Appendix: Past Progress (As of 9:00 am, December 1, 2011) (PDF 185KB)
Appendix: Past Progress (From March 11, 2011 to July 31, 2011) (PDF 225KB)
* Revised past progress