search



Corporate Information

 
Press Release (Nov 19,2011)
Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 3:00 pm, November 19)
Due to the Tohoku-Chihou-Taiheiyou-Oki Earthquake which occurred on March 
11, 2011, TEPCO's facilities including our nuclear power stations have been 
severely damaged. We deeply apologize for the anxiety and inconvenience 
caused.
With regard to the accident at Fukushima Daiichi Nuclear Power Station, on 
April 17, we have compiled the roadmap towards restoration from the 
accident and then we updated the progress status of roadmap considering the 
current situation, on July 19. Accomplishment of the Step1 target 
"Radiation dose is in steady decline" has been confirmed. On November 17, 
we updated the further progress. 
By bringing the reactors and spent fuel pools to a stable cooling condition 
and mitigating the release of radioactive materials, we will make every 
effort to enable evacuees to return to their homes and for all citizens to 
be able to secure a sound life.

Below is the status of TEPCO's major facilities.

* The underlined parts are the updates from the previous press release.

[Nuclear Power Station]  

·Fukushima Daiichi Nuclear Power Station: Unit 1 to 3: shut down due to 
 the earthquake
  (Units 4 to 6: outage due to regular inspections)

- At 10:47 pm on November 18, desalination plant (RO) unit 2-2 suspended 
  due to automatic suspend of a high pressure pump and a booster pump. The 
  research is currently underway. There is no impact for water injection to 
  the reactor because of enough fresh water stock.

- Around 11:00 pm on November 18, it was confirmed that coolant water 
  temperature at the heat exchange facility exit of unit 3 alternative 
  cooling facility for the fuel spent pool tends to increase (16.5°C at 8 pm 
  → 17.3°C at 11 pm). At 7:00 am on November 19, it was confirmed main tap 
  for watering was closed. The temperature decreased after tap opening 
  (19.5°C at 5 am → 17.9°C at 8 am). The research for tap close is 
  currently underway.

·Fukushima Daini Nuclear Power Station:
 Units 1 to 4: shutdown due to the earthquake

·Kashiwazaki Kariwa Nuclear Power Station: Units 5, 6: under normal 
 operation
  (Units 1 to 4 and 7: outage due to regular inspections)

[Thermal Power Station]
- Power supply has returned to normal and facilities damaged by the 
  earthquake are now being handled in a timely manner.

[Hydro Power Station]
- Power supply has returned to normal and facilities damaged by the 
  earthquake are now being handled in a timely manner.

[Impacts on Transmission Facilities]
- Power supply has returned to normal and facilities damaged by the 
  earthquake are now being handled in a timely manner.

[Impacts on Power Supply and Demand Balance]
This winter, there will be some minus factors such as the regular 
inspection of Unit 5 at Kashiwazaki-Kariwa Nuclear Power Station. On the 
other hand, there will be several plus factors such as the recovery of the 
common thermal power stations which suffered the earthquake. As a result, 
we expect to secure 54.9 GW (at the end of December), 54.6 GW (at the end 
of January), 53.7 GW (at the end of February) supply power. 
Compared to the maximum demand in the last winter, which is 51.5 GW, we 
will have 2.2 - 3.4 GW generation reserve margin.

We expect to maintain stable power supply this winter, however, as there 
remains possibilities of unplanned shutdowns at our power stations and 
growth in the demand according to the rapid change in the temperature, we 
would like to ask your reasonable effort to save electricity.

We will continue to make our efforts to maintain stable operation and 
maintenance of the power facilities in order to "prevent in principle" the 
planned blackouts and secure power supply.

Appendix: Past Progress (As of 3:00 pm, November 19, 2011) (PDF 224KB)

Appendix: Past Progress (From March 11, 2011 to July 31, 2011) (PDF 225KB)

* Revised past progress


back to page top


to TOP