Due to the Tohoku-Chihou-Taiheiyou-Oki Earthquake which occurred on March
11, 2011, TEPCO's facilities including our nuclear power stations have been
severely damaged. We deeply apologize for the anxiety and inconvenience
caused.
With regard to the accident at Fukushima Daiichi Nuclear Power Station, on
April 17, we have compiled the roadmap towards restoration from the
accident and then we updated the progress status of roadmap considering
the current situation, on July 19. Accomplishment of the Step1 target
"Radiation dose is in steady decline" has been confirmed. On October 17,
we updated the further progress.
By bringing the reactors and spent fuel pools to a stable cooling condition
and mitigating the release of radioactive materials, we will make every
effort to enable evacuees to return to their homes and for all citizens to
be able to secure a sound life.
Below is the status of TEPCO's major facilities.
* The underlined parts are the updates from the previous press release.
[Nuclear Power Station]
· Fukushima Daiichi Nuclear Power Station: Unit 1 to 3: shut down due to
the earthquake
(Units 4 to 6: outage due to regular inspections)
- At 9:15 am on November 17, at unit 1 and 2 emergency reactor injection
line, the additional installation work for water flow adjusting valve
was commenced to better control the amount of water injection, and
completed at 1:09 pm on the same day. Water injection to reactor had
been done through regular reactor water injection line, and therefore
the additional installation work above had no impact to water injection.
- At 10 am on November 17, accumulated water at the basement of Unit 6
Turbine Building was started to transfer to Temporary tanks.
- At around 10:50 am on November 17, water leakage from pin holes at one
point of freshwater transfer line, and three points at concentrated
water transfer line after desalination process, was confirmed by
partner companies' worker who was patrolling at desalination apparatus.
At around 2:30 pm on the same day, while water transfer was continued
through fresh water transfer line, at the same time, running leakage
repair (repaired by tapes) was implemented and completed (leakage
amount: approx. 1liter). Cesium adsorption apparatus, 2nd adsorption
apparatus and concentrated evaporation apparatus continued operation,
and therefore there is no major effect with processing accumulated
water. Also, concentrated water transfer line is currently not being
used, and is isolated.
- At 1:15 pm on November 17, hydrazine was injected to Unit 4 Spent Fuel
Pool through circulating cooling system, and finished the injection at
2:50 pm on the same day.
- At 1:32 pm on November 17, in order to clean up the 1st system strainer
of Unit 3 spent fuel pool circulating cooling system as measures for
an alert caused by decrease of suction pressure at 1st system pump of
circulating cooling system, circulating cooling was temporarily stopped
(Water temperature of spent fuel pool at the time that circulating
cooling was stopped: approx. 19.2 °C). At 2:55 pm on the same day, the
cleaning of the 1st system strainer by reverse flow washing, the
alternative cooling was resumed (Water temperature of spent fuel pool
at the time that circulating cooling was resumed: approx. 18.8 °C, which
was assumed that water in the skimmer surge tank was cooled down by
ambient air so that the water temperature of spent fuel pool when the
circulating cooling was resumed was lower than that when the
circulating cooling was stopped.).
- At 2:58 pm on November 17, an alarm of Unit 4 spent fuel pool
circulating cooling system was sounded, and the system automatically
shut down. The cause of the alarm is currently under investigation.
· Fukushima Daini Nuclear Power Station:
Units 1 to 4: shutdown due to the earthquake
· Kashiwazaki Kariwa Nuclear Power Station:
Units 5, 6: under normal operation
(Units 1 to 4 and 7: outage due to regular inspections)
[Thermal Power Station]
- Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Hydro Power Station]
- Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Impacts on Transmission Facilities]
- Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Impacts on Power Supply and Demand Balance]
This winter, there will be some minus factors such as the regular
inspection of Unit 5 at Kashiwazaki-Kariwa Nuclear Power Station. On the
other hand, there will be several plus factors such as the recovery of the
common thermal power stations which suffered the earthquake. As a result,
we expect to secure 54.9 GW (at the end of December), 54.6 GW (at the end
of January), 53.7 GW (at the end of February) supply power.
Compared to the maximum demand in the last winter, which is 51.5 GW, we
will have 2.2 - 3.4 GW generation reserve margin.
We expect to maintain stable power supply this winter, however, as there
remains possibilities of unplanned shutdowns at our power stations and
growth in the demand according to the rapid change in the temperature, we
would like to ask your reasonable effort to save electricity.
We will continue to make our efforts to maintain stable operation and
maintenance of the power facilities in order to "prevent in principle"
the planned blackouts and secure power supply.
Appendix: Past Progress (As of 3:00 pm, November 17, 2011) (PDF 151KB)
Appendix: Past Progress (From March 11, 2011 to July 31, 2011) (PDF 225KB)
* Revised past progress