Due to the Tohoku-Chihou-Taiheiyou-Oki Earthquake which occurred on March
11, 2011, TEPCO's facilities including our nuclear power stations have been
severely damaged. We deeply apologize for the anxiety and inconvenience
caused.
With regard to the accident at Fukushima Daiichi Nuclear Power Station, on
April 17, we have compiled the roadmap towards restoration from the
accident and then we updated the progress status of roadmap considering the
current situation, on July 19. Accomplishment of the Step1 target
"Radiation dose is in steady decline" has been confirmed. On October 17, we
updated the further progress.
By bringing the reactors and spent fuel pools to a stable cooling condition
and mitigating the release of radioactive materials, we will make every
effort to enable evacuees to return to their homes and for all citizens to
be able to secure a sound life.
Below is the status of TEPCO's major facilities.
*The underlined parts are the updates from the previous press release.
[Nuclear Power Station]
· Fukushima Daiichi Nuclear Power Station: Unit 1 to 3: shut down due to
the earthquake
(Units 4 to 6: outage due to regular inspections)
* At 1:29 pm on November 14, injection of hydrazine was started into the
Unit 2 spent fuel pool through the circulating cooling system. At 3:14 pm
on the same day, the injection was finished.
* From November 15, due to cleanup work in order to prevent performance
deterioration of pump caused by inletting sand or other materials piled
up at the bottom of pump room of intake channel of Unit 6, Residual Heat
Removal System (A) was shutdown, and stopped cooling the reactor. And
Seawater pump of Equipment Water Cooing System (A) was shutdown, and
stopped cooling the spent fuel pool. The stop is scheduled from 7:00 am
to 5:00 pm everyday, and reactor water temperature will rise by approx.
12°C per day, and spent fuel pool water temperature will rise by approx.
3°C per day. (The cleanup work is planned to be finished in a week.)
* On November 14, sampling survey of gas at gas management system of Unit 2
primary containment vessel was implemented. According to its analysis, it
is considered that recriticality was not occurred because radioactive
Xe-135 at the entrance of gas management system of Unit 2 was below the
detection limit (9.2x10-2Bq/cm3)
· Fukushima Daini Nuclear Power Station:
Units 1 to 4: shutdown due to the earthquake
· Kashiwazaki Kariwa Nuclear Power Station:
Units 5, 6: under normal operation
(Units 1 to 4 and 7: outage due to regular inspections)
[Thermal Power Station]
-Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Hydro Power Station]
-Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Impacts on Transmission Facilities]
-Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Impacts on Power Supply and Demand Balance]
This winter, there will be some minus factors such as the regular
inspection of Unit 5 at Kashiwazaki-Kariwa Nuclear Power Station. On the
other hand, there will be several plus factors such as the recovery of the
common thermal power stations which suffered the earthquake. As a result,
we expect to secure 54.9 GW (at the end of December), 54.6 GW (at the end
of January), 53.7 GW (at the end of February) supply power.
Compared to the maximum demand in the last winter, which is 51.5 GW, we
will have 2.2 - 3.4 GW generation reserve margin.
We expect to maintain stable power supply this winter, however, as there
remains possibilities of unplanned shutdowns at our power stations and
growth in the demand according to the rapid change in the temperature, we
would like to ask your reasonable effort to save electricity.
We will continue to make our efforts to maintain stable operation and
maintenance of the power facilities in order to "prevent in principle" the
planned blackouts and secure power supply.
Appendix: Past Progress (As of 9:00 am, November 15, 2011) (PDF 145KB)