search



Corporate Information

 
Press Release (Nov 14,2011)
Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 3:00 pm, November 14)
Due to the Tohoku-Chihou-Taiheiyou-Oki Earthquake which occurred on March 
11, 2011, TEPCO's facilities including our nuclear power stations have 
been severely damaged. We deeply apologize for the anxiety and 
inconvenience caused.
With regard to the accident at Fukushima Daiichi Nuclear Power Station, on 
April 17, we have compiled the roadmap towards restoration from the 
accident and then we updated the progress status of roadmap considering 
the current situation, on July 19. Accomplishment of the Step1 target 
"Radiation dose is in steady decline" has been confirmed. On October 17, 
we updated the further progress. 
By bringing the reactors and spent fuel pools to a stable cooling 
condition and mitigating the release of radioactive materials, we will 
make every effort to enable evacuees to return to their homes and for all 
citizens to be able to secure a sound life.

Below is the status of TEPCO's major facilities.

* The underlined parts are the updates from the previous press release.

[Nuclear Power Station]

· Fukushima Daiichi Nuclear Power Station: Unit 1 to 3: shut down due to 
  the earthquake
  (Units 4 to 6: outage due to regular inspections)

* At 0:32 pm on November 14, an alarm went off at the measure (Continuous
  Dust Monitor) installed in front of the main gate, which had
  continuously measured the radioactivity concentration in air. The cause
  of the alarm was assumed to be a defect of the equipment by clogged
  filters. Around 1:08 pm on the same day, the measure was reset and the
  monitoring was resumed. The dust concentration near the main gate was
  measured 6 x 10-6 [Bq/㎤], which was less than the reference measure
  for wearing a full face mask, 1 x 10-4 [Bq/㎤]. Although an instruction
  to wear a full face mask since 0:39 pm was given responding the alarm,
  around 2:11 pm on the same day it was announced that the workers did not
  have to wear a full face mask as per normal

* At 1:29 pm on November 14, injection of hydrazine was started into the 
  Unit 2 spent fuel pool through the circulating cooling system.

· Fukushima Daini Nuclear Power Station:
  Units 1 to 4: shutdown due to the earthquake

· Kashiwazaki Kariwa Nuclear Power Station:
  Units 5, 6: under normal operation
  (Units 1 to 4 and 7: outage due to regular inspections)

[Thermal Power Station]
-Power supply has returned to normal and facilities damaged by the 
 earthquake are now being handled in a timely manner.

[Hydro Power Station]
-Power supply has returned to normal and facilities damaged by the 
 earthquake are now being handled in a timely manner.

[Impacts on Transmission Facilities]
-Power supply has returned to normal and facilities damaged by the 
 earthquake are now being handled in a timely manner.

[Impacts on Power Supply and Demand Balance]
This winter, there will be some minus factors such as the regular 
inspection of Unit 5 at Kashiwazaki-Kariwa Nuclear Power Station. On the 
other hand, there will be several plus factors such as the recovery of the 
common thermal power stations which suffered the earthquake. As a result, 
we expect to secure 54.9 GW (at the end of December), 54.6 GW (at the end 
of January), 53.7 GW (at the end of February) supply power. 
Compared to the maximum demand in the last winter, which is 51.5 GW, we 
will have 2.2 - 3.4 GW generation reserve margin.

We expect to maintain stable power supply this winter, however, as there 
remains possibilities of unplanned shutdowns at our power stations and 
growth in the demand according to the rapid change in the temperature, we 
would like to ask your reasonable effort to save electricity. 

We will continue to make our efforts to maintain stable operation and 
maintenance of the power facilities in order to "prevent in principle" the 
planned blackouts and secure power supply.

Appendix: Past Progress (As of 3:00 pm, November 14, 2011) (PDF 144KB)
Appendix: Past Progress (From March 11, 2011 to July 31, 2011) (PDF 225KB)

* Revised past progress
back to page top


to TOP