Due to the Tohoku-Chihou-Taiheiyou-Oki Earthquake which occurred on March
11, 2011, TEPCO's facilities including our nuclear power stations have been
severely damaged. We deeply apologize for the anxiety and inconvenience
caused.
With regard to the accident at Fukushima Daiichi Nuclear Power Station, on
April 17, we have compiled the roadmap towards restoration from the
accident and then we updated the progress status of roadmap considering the
current situation, on July 19. Accomplishment of the Step1 target
"Radiation dose is in steady decline" has been confirmed. On October 17, we
updated the further progress.
By bringing the reactors and spent fuel pools to a stable cooling condition
and mitigating the release of radioactive materials, we will make every
effort to enable evacuees to return to their homes and for all citizens to
be able to secure a sound life.
Below is the status of TEPCO's major facilities.
* The underlined parts are the updates from the previous press release.
[Nuclear Power Station]
·Fukushima Daiichi Nuclear Power Station: Unit 1 to 3: shut down due to
the earthquake
(Units 4 to 6: outage due to regular inspections)
* At 3:05 pm on November 8, for the purpose of switching off accumulated
water transfer pump of unit 3 for enhancement work of electricity source,
transfer of accumulated water of underground of turbine building of unit
3 to centralized radiation waste treatment facility (miscellaneous solid
waste volume reduction treatment facility (high temperature incinerator
building) was stopped.
* At 4:05 pm on November 8, water injection to reactor of unit 3, as
decrease of injection rate from feed water system was observed, injection
rate was adjusted to approx. 3.0m3/h (water injection continues from core
spray system at approx. 8.0m3/h).
* At 4:23 am on November 8, as allophone was observed from the motor of
cesium adsorption treatment water transfer pump (B), cesium adsorption
apparatus was stopped. After switched to (A) pump, at 4:54 pm, it was
restarted and reached to normal operation flow (approx. 18m3/h) at 5:00
pm. We will investigate the cause. As the apparatus stop time was short,
there was no significant effect on the water treatment.
* At 2:24 am on November 8, we manually stopped the boiler of evaporative
concentration apparatus in the water desalinations since alarm worked and
indicated decrease of water level in boiler water supply tank at 2:20 am.
Then, we stopped evaporative concentration apparatus 3B at 2:28 am ad 3C
at 2:31 am. Although all the evaporative concentration apparatus stopped,
water treatment by the water desalinations (RO membrane system) and water
injection to the reactors have been continued. Causes will be
investigated in the future. Thereafter, as a result of the inspection of
inlet strainer of boiler make up water transfer pumps (A) and (B),
plugging was found due to water scale of filtered water attached to
inside of the pipe, after removing those contaminations, evaporated
concentration apparatus 3B and 3C was restarted at 5:08 pm and at 6:01 am
on the same day respectively. Cleaning of strainer will be conducted at
appropriate timing.
* Cooling system of spent fuel pool was stopped at 5:41 am for unit 2 and
at 5:43 am for unit 1 due to the switching work of electricity to enhance
security of electricity source. Both system will be shut down until 4:30
pm. The temperature at the time was 22°C for unit 1 and 24°C for unit 2
and the temperature of spent fuel pool will be estimated to increase
around 1 - 2°C for unit 1 and about 3°C for unit 2.
·Fukushima Daini Nuclear Power Station:
Units 1 to 4: shutdown due to the earthquake
·Kashiwazaki Kariwa Nuclear Power Station:
Units 5, 6: under normal operation
(Units 1 to 4 and 7: outage due to regular inspections)
[Thermal Power Station]
- Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Hydro Power Station]
- Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Impacts on Transmission Facilities]
- Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Impacts on Power Supply and Demand Balance]
This winter, there will be some minus factors such as the regular
inspection of Unit 5 at Kashiwazaki-Kariwa Nuclear Power Station. On the
other hand, there will be several plus factors such as the recovery of the
common thermal power stations which suffered the earthquake. As a result,
we expect to secure 54.9 GW (at the end of December), 54.6 GW (at the end
of January), 53.7 GW (at the end of February) supply power.
Compared to the maximum demand in the last winter, which is 51.5 GW, we
will have 2.2 - 3.4 GW generation reserve margin.
We expect to maintain stable power supply this winter, however, as there
remains possibilities of unplanned shutdowns at our power stations and
growth in the demand according to the rapid change in the temperature, we
would like to ask your reasonable effort to save electricity.
We will continue to make our efforts to maintain stable operation and
maintenance of the power facilities in order to "prevent in principle" the
planned blackouts and secure power supply.
Appendix: Past Progress (As of 9:00 am, November 9, 2011) (PDF 140KB)
Appendix: Past Progress (From March 11, 2011 to July 31, 2011) (PDF 225KB)
* Revised past progress