Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 3:00 pm, August 28)
Due to the Tohoku-Chihou-Taiheiyou-Oki Earthquake which occurred on March 
11, 2011, TEPCO's facilities including our nuclear power stations have 
been severely damaged. We deeply apologize for the anxiety and 
inconvenience caused.
With regard to the accident at Fukushima Daiichi Nuclear Power Station, on 
April 17, we have compiled the roadmap towards restoration from the 
accident and then we updated the progress status of roadmap considering 
the current situation, on July 19. Accomplishment of the Step1 target 
"Radiation dose is in steady decline" has been confirmed. On August 17, we 
updated the further progress. 
By bringing the reactors and spent fuel pools to a stable cooling 
condition and mitigating the release of radioactive materials, we will 
make every effort to enable evacuees to return to their homes and for all 
citizens to be able to secure a sound life.

Below is the status of TEPCO's major facilities.

*New items are underlined 

*At 11:45 pm on August 27, we stopped Water Desalination 1A (Type of
 Reverse Osmosis Membrane) because its filter needs to be replaced. At
 10:54 am on August 28, we restarted the operation after changing the
 filter.
*From 8:10 am to 2:25 pm on August 28, we conducted dust sampling at
 the upper part of reactor building of Unit 3 using a large crane vehicle.

[Nuclear Power Station]
-Fukushima Daiichi Nuclear Power Station:
   Units 1 to 3: shutdown due to the earthquake
   (Units 4 to 6: outage due to regular inspections) 

-Fukushima Daini Nuclear Power Station:
   Units 1 to 4: shutdown due to the earthquake

-Kashiwazaki Kariwa Nuclear Power Station:
   Units 5, 6: under normal operation
   (Units 1 to 4 and 7: outage due to regular inspection)

[Thermal Power Station]
-Power supply has returned to normal and facilities damaged by the 
 earthquake are now being handled in a timely manner.

[Hydro Power Station]
-Power supply has returned to normal and facilities damaged by the 
 earthquake are now being handled in a timely manner.

[Impacts on Transmission Facilities]
-Power supply has returned to normal and facilities damaged by the 
 earthquake are now being handled in a timely manner.

[Perspective of Power Supply and Demand Balance in this Summer]
-In August and September, we forecast the maximum supply will be 
 56.1 GW, and the peak demand 48.9 GW.

We apologize for the inconvenience this may cause and appreciate for your 
cooperation to save electricity.

Appendix: Past Progress (As of 3:00 pm, August 28, 2011) (PDF 245KB)
Appendix: Past Progress (From March 11, 2011 to July 31, 2011) (PDF 225KB)

* Revised past progress