Due to the Tohoku-Chihou-Taiheiyou-Oki Earthquake which occurred on March
11, 2011, TEPCO's facilities including our nuclear power stations have been
severely damaged. We deeply apologize for the anxiety and inconvenience
caused.
With regard to the accident at Fukushima Daiichi Nuclear Power Station, on
April 17, we have compiled the roadmap towards restoration from the
accident and then we updated the progress status of roadmap considering the
current situation, on July 19. Accomplishment of the Step1 target
"Radiation dose is in steady decline" has been confirmed.
By bringing the reactors and spent fuel pools to a stable cooling condition
and mitigating the release of radioactive materials, we will make every
effort to enable evacuees to return to their homes and for all citizens to
be able to secure a sound life.
Below is the status of TEPCO's major facilities.
*Updates from previous press release are underlined.
[Nuclear Power Station]
Fukushima Daiichi Nuclear Power Station:
Units 1 to 3: shutdown due to the earthquake
(Units 4 to 6: outage due to regular inspections)
- At 10:00 am on August 11, we started transferring of accumulated water
from inside the Unit 6 turbine building to temporary tanks. At 4:00 pm on
the same day, we finished transfer.
- At 3:00 pm on August 11, we confirmed that the circuit breaker supplying
power to the charger for control power of the temporary power board for
Units 1 and 2 was open. At 4:00 pm on the same day, we confirmed that the
voltage of the back-up battery for control power dropped. At 1:21 am on
August 12, we replaced the battery and the charger and resumed receiving
power.
- At 3:22 am on August 12, an M 6.0 earthquake with the seismic center at
offshore of Fukushima prefecture occurred. Events confirmed are as
follows:
•The boiler for the vaporization and condensation system at the water
treatment facility stopped. At 3:42 am on the same day, we restarted
the boiler and resumed vaporization and condensation.
•At 3:52 am on the same day, we confirmed that the reactor water
injection rate for Unit 1 dropped to 3.2m3/h. At 3:52 am on the same
day, we adjusted the rate to 3.9m3/h. Reactor water injection for Units
1 to 3 is continuing.
•At 5:06 am on the same day, we confirmed that one out of two of the
temporary control air compressor, Unit 1 stopped. As we could not
restart this, at 6:44 am on the same day, we started the back-up
diesel-driven air compressor. There is no impact on the nitrogen gas
injection for Unit 1.
•At 5:27 am on the same day, we found very small volume of water leakage
from a hose, primary system, alternative Spent Fuel Pool cooling system
located in the rad waste treatment building, Unit 4. We are planning to
replace the hose.
Fukushima Daini Nuclear Power Station:
Units 1 to 4: shutdown due to the earthquake
Kashiwazaki Kariwa Nuclear Power Station:
Units 5, 6, 7: normal operation
(Units 1 to 4: outage due to regular inspection)
[Thermal Power Station]
- Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Hydro Power Station]
- Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Impacts on Transmission Facilities]
- Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Perspective of Power Supply and Demand Balance in this Summer]
In regard to the supply side in this summer, taking in account of the
acceleration of restoration schedule for Hirono Thermal Power Station, more
purchase of privately generated power, and excluding the power supply from
60Hz areas which had been planned (due to the current difficult situation),
supply capacity outlook is amended to 56.1GW at the end of August.
Also, in order to support the supply and demand balance in the Tohoku area,
which suffered severe damage from the quake, we would like to supply
maximum of 1.4GW to Tohoku Electric Power Company by thoroughly
implementing both supply and demand countermeasures. The supply capacity in
this regard will be 54.7GW at the end of August.
Estimated peak demand of 55GW for this summer is 5GW lower than that of
last year. This incorporates the saving of electricity from "Outline of
Countermeasures for Power Supply and Demand During Summertime" and
restoration from decrease of production due to the quake.
As the occurrence of unplanned outage of aged thermal power stations or
sudden increase of demand due to unexpected high temperature during summer
may cause difficulties in maintaining stable demand supply balance, in
order to continue to avoid rolling blackouts, we will steadily maintain
supply capacity, and continue our efforts on reliable operation and
maintenance of power facilities.
We apologize for the inconvenience this may cause and appreciate for your
cooperation to save electricity.
Appendix: Past Progress (PDF 246KB)
* Revised past progress