Due to the Tohoku-Chihou-Taiheiyou-Oki Earthquake which occurred on March
11, 2011, TEPCO's facilities including our nuclear power stations have been
severely damaged. We deeply apologize for the anxiety and inconvenience
caused.
With regard to the accident at Fukushima Daiichi Nuclear Power Station, on
April 17, we have compiled the roadmap towards restoration from the
accident and then we updated the progress status of roadmap considering the
current situation, on July 19. Accomplishment of the Step1 target
"Radiation dose is in steady decline" has been confirmed.
By bringing the reactors and spent fuel pools to a stable cooling condition
and mitigating the release of radioactive materials, we will make every
effort to enable evacuees to return to their homes and for all citizens to
be able to secure a sound life.
Below is the status of TEPCO's major facilities.
*Updates from previous press release are underlined.
[Nuclear Power Station]
Fukushima Daiichi Nuclear Power Station:
Units 1 to 3: shutdown due to the earthquake
(Units 4 to 6: outage due to regular inspections)
- At 8:20 pm on August 8, Water Treatment Facility has stopped due to the
water level gauge's error alarm of SPT tank. Subsequently, we confirmed
no problems with Water Treatment Facility and the facility has started at
10:22 pm on the same day and resumed operation at 10:45 pm.
- Since SPT waste liquid pump and SPT receiving water transfer pump
stopped, an alarm showed low level of water at waste RO supply tank at
1:50 am on August 9 and Water Desalinations automatically stopped.
- At 10:00 am on August 8, we resumed transferring low-level accumulated
water to Mega Float which had been transferred from turbine building of
Unit 6 to temporary tank. At 5:00 pm on the same day, we finished
transferring.
- At 11:00 am on August 8, we started transferring accumulated water from
the underground level of reactor building of Unit 6 to a temporary tank.
At 4:00 pm on the same day, we finished transferring.
- At 9:49 am on August 8, we started transferring accumulated water from
miscellaneous solid waste volume reduction treatment building (high
temperature incinerator building) to process main building at centralized
radiation waste treatment facility. At 6:32 pm on the same day, we
finished transferring.
Fukushima Daini Nuclear Power Station:
Units 1 to 4: shutdown due to the earthquake
- At 9:31 am on August 8, among 7 monitoring posts installed in the site
boundary, we started regular inspection on No.5. At 8:00 pm on the same
day, we finished inspection.
Kashiwazaki Kariwa Nuclear Power Station:
Units 5, 6, 7: normal operation
(Units 1 to 4: outage due to regular inspection)
[Thermal Power Station]
- Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Hydro Power Station]
- Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Impacts on Transmission Facilities]
- Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Perspective of Power Supply and Demand Balance in this Summer]
In regard to the supply side in this summer, taking in account of the
acceleration of restoration schedule for Hirono Thermal Power Station, more
purchase of privately generated power, and excluding the power supply from
60Hz areas which had been planned (due to the current difficult situation),
supply capacity outlook is amended to 57.2GW at the end of July, and 56.1GW
at the end of August.
Also, in order to support the supply and demand balance in the Tohoku area,
which suffered severe damage from the quake, we would like to supply
maximum of 1.4GW to Tohoku Electric Power Company by thoroughly
implementing both supply and demand countermeasures. The supply capacity in
this regard will be 55.8GW at the end of July, and 54.7GW at the end of
August.
Estimated peak demand of 55GW for this summer is 5GW lower than that of
last year. This incorporates the saving of electricity from "Outline of
Countermeasures for Power Supply and Demand During Summertime" and
restoration from decrease of production due to the quake.
As the occurrence of unplanned outage of aged thermal power stations or
sudden increase of demand due to unexpected high temperature during summer
may cause difficulties in maintaining stable demand supply balance, in
order to continue to avoid rolling blackouts, we will steadily maintain
supply capacity, and continue our efforts on reliable operation and
maintenance of power facilities.
We apologize for the inconvenience this may cause and appreciate for your
cooperation to save electricity.
Appendix: Past Progress (PDF 235KB)
* Revised past progress