Due to the Tohoku-Chihou-Taiheiyou-Oki Earthquake which occurred on March
11, 2011, TEPCO's facilities including our nuclear power stations have been
severely damaged. We deeply apologize for the anxiety and inconvenience
caused.
With regard to the accident at Fukushima Daiichi Nuclear Power Station, on
April 17, we have compiled the roadmap towards restoration from the accident
and then we updated the progress status of roadmap considering the current
situation, on July 19. Accomplishment of the Step1 target "Radiation dose
is in steady decline" has been confirmed.
By bringing the reactors and spent fuel pools to a stable cooling condition
and mitigating the release of radioactive materials, we will make every
effort to enable evacuees to return to their homes and for all citizens to
be able to secure a sound life.
Below is the status of TEPCO's major facilities.
*Updates are underlined.
[Nuclear Power Station]
Fukushima Daiichi Nuclear Power Station:
Units 1 to 3: shutdown due to the earthquake
(Units 4 to 6: outage due to regular inspections)
- At 5:50 pm on August 4, decrease of water injection volume into Unit 2
reactor was confirmed and it was adjusted to approx. 3.8 m3/h.
- At 8:42 am on August 5, we started transferring accumulated water from
the basement of Unit 3 turbine building to Centralized Radiation Waste
Treatment Facility (Process Main Building).
- At 5:32 am on August 4, we stopped operation of the water treatment
facility in order to improve the flow rate. After the work to improve
the flow rate, we started the water treatment facility at 3:30 pm and
water treatment at 4:13 pm on the same day.
- At 6:55 pm on August 4, decontamination facility automatically stopped
due to the stop of chemical injection pumps for ultra-high speed
coagulation sedimentation facility and we stopped the water treatment
facility. We checked the soundness of the stopped pumps and started water
treatment facility at 8:30 pm, and water treatment at 8:50 pm on the same
day.
- At 2:12 am on August 5, a process error alarm was generated and we
stopped the water treatment facility. We started the water treatment
facility at 4:03 am and water treatment at 4:21 am on the same day.
- Around 7 pm on August 4, leakage was found from the flange of the hoses
to transfer filtrate water which has been used for salt cleansing in the
vessel of cesium adsorption facility at On-site Bunker Building. The
cause is under investigation.
- At 3:32 pm on August 4, we started fresh-water injection using
alternative water injection line in order to fill Skimmer Surge Tank of
Unit 4 with water and finished the injection at 3:32 pm on the same day.
Fukushima Daini Nuclear Power Station:
Units 1 to 4: shutdown due to the earthquake
- At 9:31 am on August 4, we started a regular inspection about one of the
7 monitoring posts (No.3) installed around the site boundary and
completed at 6 pm on August 4.
Kashiwazaki Kariwa Nuclear Power Station:
Units 1, 5, 6, 7: normal operation
(Units 2 to 4: outage due to regular inspection)
[Thermal Power Station]
- Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Hydro Power Station]
- Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Impacts on Transmission Facilities]
- Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Perspective of Power Supply and Demand Balance in this Summer]
In regard to the supply side in this summer, taking in account of the
acceleration of restoration schedule for Hirono Thermal Power Station, more
purchase of privately generated power, and excluding the power supply from
60Hz areas which had been planned (due to the current difficult situation),
supply capacity outlook is amended to 57.2GW at the end of July, and 56.1GW
at the end of August.
Also, in order to support the supply and demand balance in the Tohoku area,
which suffered severe damage from the quake, we would like to supply maximum
of 1.4GW to Tohoku Electric Power Company by thoroughly implementing both
supply and demand countermeasures. The supply capacity in this regard will
be 55.8GW at the end of July, and 54.7GW at the end of August.
Estimated peak demand of 55GW for this summer is 5GW lower than that of
last year. This incorporates the saving of electricity from "Outline of
Countermeasures for Power Supply and Demand During Summertime" and
restoration from decrease of production due to the quake.
As the occurrence of unplanned outage of aged thermal power stations or
sudden increase of demand due to unexpected high temperature during summer
may cause difficulties in maintaining stable demand supply balance, in
order to continue to avoid rolling blackouts, we will steadily maintain
supply capacity, and continue our efforts on reliable operation and
maintenance of power facilities.
We apologize for the inconvenience this may cause and appreciate for your
cooperation to save electricity.
Appendix: Past Progress (PDF 230KB)
* Revised past progress