Due to the Tohoku-Chihou-Taiheiyou-Oki Earthquake which occurred on March
11, 2011, TEPCO's facilities including our nuclear power stations have been
severely damaged. We deeply apologize for the anxiety and inconvenience
caused.
With regard to the accident at Fukushima Daiichi Nuclear Power Station, on
April 17, we have compiled the roadmap towards restoration from the
accident and then we updated the progress status of roadmap considering the
current situation, on July 19. Accomplishment of the Step1 target
"Radiation dose is in steady decline" has been confirmed.
By bringing the reactors and spent fuel pools to a stable cooling condition
and mitigating the release of radioactive materials, we will make every
effort to enable evacuees to return to their homes and for all citizens to
be able to secure a sound life.
Below is the status of TEPCO's major facilities.
*Updates are underlined.
[Nuclear Power Station]
Fukushima Daiichi Nuclear Power Station:
Units 1 to 3: shutdown due to the earthquake
(Units 4 to 6: outage due to regular inspections)
- From 5:52 am on August 3, in order to replace the nitrogen gas injector
device, we stopped nitrogen gas injection into the Primary Containment
Vessel of Units 1 to 3. After completion of the replacement, we restarted
injection of nitrogen gas into Unit 1 at 8:33 am, into Unit 2 at 8:29 am,
into Unit 3 at 8:29. (Regarding Unit 2, we continued injection of
nitrogen gas with a backup injector from 5:58 am to 8:27 am.)
- At 4:10 pm on July 30, we started transfer of the accumulated water from
the vertical shaft of the Turbine Building of Unit 2 to Centralized
Radiation Waste Treatment Facility(Process Main Building). We stopped
transfer at 6:49 pm on August 2.
- At 5:05 pm on August 2, in order to fill water in the skimmer surge tank
of Unit 4. we started injection of fresh water using an alternate water
injection line. We stopped injection at 5:37 pm.
- At 10:00 am on August 2, we resumed transferring the accumulated low
concentrated water which was transferred from the turbine building of
Unit 6 to the temporary tank to Mega Float. We stopped transfer at 5:00
pm.
- At 11:00 am on August 2, we resumed transferring the accumulated water in
the basement in the turbine building of Unit 6 to the temporary tank. We
stopped transfer at 4:00 pm.
Fukushima Daini Nuclear Power Station:
Units 1 to 4: shutdown due to the earthquake
Kashiwazaki Kariwa Nuclear Power Station:
Units 1, 5, 6, 7: normal operation
(Units 2 to 4: outage due to regular inspection)
[Thermal Power Station]
- Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Hydro Power Station]
- Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Impacts on Transmission Facilities]
- Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Perspective of Power Supply and Demand Balance in this Summer]
In regard to the supply side in this summer, taking in account of the
acceleration of restoration schedule for Hirono Thermal Power Station, more
purchase of privately generated power, and excluding the power supply from
60Hz areas which had been planned (due to the current difficult situation),
supply capacity outlook is amended to 57.2GW at the end of July, and 56.1GW
at the end of August.
Also, in order to support the supply and demand balance in the Tohoku area,
which suffered severe damage from the quake, we would like to supply
maximum of 1.4GW to Tohoku Electric Power Company by thoroughly
implementing both supply and demand countermeasures. The supply capacity in
this regard will be 55.8GW at the end of July, and 54.7GW at the end of
August.
Estimated peak demand of 55GW for this summer is 5GW lower than that of
last year. This incorporates the saving of electricity from "Outline of
Countermeasures for Power Supply and Demand During Summertime" and
restoration from decrease of production due to the quake.
As the occurrence of unplanned outage of aged thermal power stations or
sudden increase of demand due to unexpected high temperature during summer
may cause difficulties in maintaining stable demand supply balance, in
order to continue to avoid rolling blackouts, we will steadily maintain
supply capacity, and continue our efforts on reliable operation and
maintenance of power facilities.
We apologize for the inconvenience this may cause and appreciate for your
cooperation to save electricity.
Appendix: Past Progress (PDF 228KB)
* Revised past progress