Due to the Tohoku-Chihou-Taiheiyou-Oki Earthquake which occurred on March
11, 2011, TEPCO's facilities including our nuclear power stations have
been severely damaged. We deeply apologize for the anxiety and
inconvenience caused.
With regard to the accident at Fukushima Daiichi Nuclear Power Station, on
April 17, we have compiled the roadmap towards restoration from the
accident and then we updated the progress status of roadmap considering
the current situation, on July 19. Accomplishment of the Step1 target
"Radiation dose is in steady decline" has been confirmed.
By bringing the reactors and spent fuel pools to a stable cooling
condition and mitigating the release of radioactive materials, we will
make every effort to enable evacuees to return to their homes and for all
citizens to be able to secure a sound life.
Below is the status of TEPCO's major facilities.
*Updates are underlined.
[Nuclear Power Station]
Fukushima Daiichi Nuclear Power Station:
Units 1 to 3: shutdown due to the earthquake
(Units 4 to 6: outage due to regular inspections)
-At 8:43 am on July 22, because we confirmed that the amount of water
injection had been lowered, we adjusted the amount to approximately
3.8m3/h.
-At 7:10 am on July 22, the circuit breaker for the bus which supplies
electricity to a part of power network in the power station opened the
circuit due to overload, resulting in the power off of the following
facilities: the alternative cooling facility for spent fuel pool at Unit
3, monitoring gauges in the reactor of Unit 3 & 4, water treatment
facilities, Main Anti-Earthquake Building, and the cooling facility of
common pool. For Main Anti-Earthquake Building, we restore its power
supply immediately using backup power generator. For reference, this
event did not affect the following operations: water injection and
nitrogen gas injection to reactor of each unit, and data of each
monitoring post.
-Later, we have switched the power supply source and have resumed power
supply for Main Anti-Earthquake Building at 9:33 am on the same day, for
monitoring gauges in the reactor of Unit 3 & 4 at 10:35 am, for the
cooling facility of common pool at 10:40 am on the same day, the
alternative cooling facility for spent fuel pool at Unit 3 at 11:50 am on
the same day. Currently, the cause of the event is under investigation.
Fukushima Daini Nuclear Power Station:
Units 1 to 4: shutdown due to the earthquake
Kashiwazaki Kariwa Nuclear Power Station:
Units 1, 5, 6, 7: normal operation
(Units 2 to 4: outage due to regular inspection)
[Thermal Power Station]
-Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Hydro Power Station]
-Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Impacts on Transmission Facilities]
-Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Perspective of Power Supply and Demand Balance in this Summer]
In regard to the supply side in this summer, taking in account of the
acceleration of restoration schedule for Hirono Thermal Power Station,
more purchase of privately generated power, and excluding the power supply
from 60Hz areas which had been planned (due to the current difficult
situation), supply capacity outlook is amended to 57.3GW at the end of
July, and 56.1GW at the end of August.
Also, in order to support the supply and demand balance in the Tohoku area,
which suffered severe damage from the quake, we would like to supply
maximum of 1.4GW to Tohoku Electric Power Company by thoroughly
implementing both supply and demand countermeasures. The supply capacity
in this regard will be 55.9GW at the end of July, and 54.7GW at the end of
August.
Estimated peak demand of 55GW for this summer is 5GW lower than that of
last year. This incorporates the saving of electricity from "Outline of
Countermeasures for Power Supply and Demand During Summertime" and
restoration from decrease of production due to the quake.
As the occurrence of unplanned outage of aged thermal power stations or
sudden increase of demand due to unexpected high temperature during summer
may cause difficulties in maintaining stable demand supply balance, in
order to continue to avoid rolling blackouts, we will steadily maintain
supply capacity, and continue our efforts on reliable operation and
maintenance of power facilities.
We apologize for the inconvenience this may cause and appreciate for your
cooperation to save electricity.
Appendix: Past Progress (PDF 215KB)
* Revised past progress