Due to the Tohoku-Chihou-Taiheiyou-Oki Earthquake which occurred on March
11, 2011, TEPCO's facilities including our nuclear power stations have
been severely damaged. We deeply apologize for the anxiety and
inconvenience caused.
With regard to the accident at Fukushima Daiichi Nuclear Power Station, on
April 17, we have compiled the roadmap towards restoration from the
accident and then we updated the roadmap considering the current situation,
on June 17. By bringing the reactors and spent fuel pools to a stable
cooling condition and mitigating the release of radioactive materials, we
will make every effort to enable evacuees to return to their homes and for
all citizens to be able to secure a sound life.
Below is the status of TEPCO's major facilities.
*Updates from previous press release are underlined.
[Nuclear Power Station]
Fukushima Daiichi Nuclear Power Station:
Units 1 to 3: shutdown due to the earthquake
(Units 4 to 6: outage due to regular inspections)
-At 6:38 am on July 15th, we found that cooling makeup water was not
sprayed in the cooling tower in the second order of circulating cooling
system in the spent fuel pool for Unit 2. At 8:22 am on the same day we
stopped the circulating pumps in the second order cooling tower and the
fans. After that, we confirmed the feed water valves from the filtering
water tanks are closed. At 11:47 am on the same we opened the valves and
confirmed feeding water from the filtering water tanks and resumed
operating the circulating pump and the fans.
-At 8:55 am on July 15th, as we found decrease of the volume of water
injection into the reactor of Unit 1, we increased the injection volume
to approx. 3.8㎥/h.
-At 10:00 am July 15, we resumed transferring low radioactive accumulate
water, which had been transferred from Unit 6 turbine building to
temporary tanks, from temporary tanks to the Mega Float.
-At 10:16 am on July 15, we activated pumps of main residual heat removal
seawater system (system B) of Unit 5 and began a trial run.
-From 10:09 am on July 13th to 11:02 am on July 15th, we transferred the
accumulated water from the vertical shaft of the Unit 2 turbine building
to Centralized Radiation Waste Treatment Facility (Process Main Building)
-From 3:15 pm on July 10th to 11:11 am on July 15th, we transferred the
accumulated water in the basement of the Unit 3 turbine building to
Centralized Radiation Waste Treatment Facility (Process Main Building)
-At 1:05 pm on July 15th, we exchanged injection hoses with new ones and
started injecting fresh water in the reactor well and equipment storage
pool.
-At 5:14 am on July 15th, we stopped the facility in order to investigate
the causes of decrease of rated flow volume of water treatment. At 2:21
pm on the same day we resume activating the facility.
Fukushima Daini Nuclear Power Station:
Units 1 to 4: shutdown due to the earthquake
Kashiwazaki Kariwa Nuclear Power Station:
Units 1, 5, 6, 7: normal operation
(Units 2 to 4: outage due to regular inspection)
[Thermal Power Station]
-Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
*With regard to Unit 4 of Hirono Thermal Power Station, we mistakenly
announced that we have been generating electricity since 5:17 pm on
July 14th. Correctly, we have been generating electricity since 5:14
pm on July 14th. Please accept our sincere apologies for this.
[Hydro Power Station]
-Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Impacts on Transmission Facilities]
-Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Perspective of Power Supply and Demand Balance in this Summer]
In regard with the supply side in this summer, taking in account of the
acceleration of restoration schedule for Hirono Thermal Power Station,
more purchase of privately generated power, and excluding the power
supply from 60Hz areas which had been planned (due to the current
difficult situation), supply capacity outlook is amended to 56.8GW at
the end of July, and 55.6GW at the end of August.
Also, in order to support balance of demand and supply in the Tohoku
area, which suffered severe damage from the quake, we would like to
supply maximum of 1.4GW to Tohoku Electric Power Company by thoroughly
implementing both supply and demand countermeasures. The supply capacity
in this regard will be 55.4GW at the end of July, and 54.2GW at the end
of August.
Estimated peak demand of 55GW for this summer is 5GW lower than that of
last year. This incorporates the saving of electricity from "Outline of
Countermeasures for Power Supply and Demand During Summertime" and
restoration from decrease of production due to the quake.
As the occurrence of unplanned outage of aged thermal power stations or
sudden increase of demand due to unexpected high temperature during summer
may cause difficulties in maintaining stable demand supply balance, in
order to continue to avoid rolling blackouts, we will steadily maintain
supply capacity, and continue our efforts on reliable operation and
maintenance of power facilities.
We apologize for the inconvenience this may cause and appreciate for your
cooperation to save electricity.
Appendix: Past Progress (PDF 399KB)
* Revised past progress