search



Corporate Information

 
Press Release (Jun 30,2011)
Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake(as of 3:00 PM, June 30)
Due to the Tohoku-Chihou-Taiheiyou-Oki Earthquake which occurred on March 
11, 2011, TEPCO's facilities including our nuclear power stations have been 
severely damaged. We deeply apologize for the anxiety and inconvenience 
caused.
With regard to the accident at Fukushima Daiichi Nuclear Power Station, on 
April 17, we have compiled the roadmap towards restoration from the 
accident and then we updated the roadmap considering the current situation, 
on June 17. By bringing the reactors and spent fuel pools to a stable 
cooling condition and mitigating the release of radioactive materials, we 
will make every effort to enable evacuees to return to their homes and for 
all citizens to be able to secure a sound life.

Below is the status of TEPCO's major facilities.
*Updates from previous press release are underlined.
[Nuclear Power Station] 
Fukushima Daiichi Nuclear Power Station: 
       Units 1 to 3: shutdown due to the earthquake 
       (Units 4 to 6: outage due to regular inspections) 

- At 10:46 am on June 30, we stopped the Accumulated Water Treatment 
  Facility, for flushing the system. At 1:35 pm on the same day, we 
  restarted the Facility. At 2:36 pm, we re-stopped the Instruments due to 
  the defect of Coagulation Setting Facility. Now, we are investigating the 
  detail. 
- At 11:30 am on June 30, we started injecting fresh water into the spent 
  fuel pool of Unit 4 using Alternative Water Injection Line. At 11:55 on 
  the same day, we finished the injection. 
- At 1:00 pm on June 30, we started transferring of low radioactive stored 
  water from temporary tank to Mega Float. Although a water blow was found 
  on the surface of the transferring hose, we cure it and confirmed no 
  leakages to outside. 
- At 3:00 pm on June 30, we started transferring of accumulated water from 
  inside of turbine building of Unit 6 to temporary tank.
Fukushima Daini Nuclear Power Station: 
       Units 1 to 4: shutdown due to the earthquake
Kashiwazaki Kariwa Nuclear Power Station: 
       Units 1, 5, 6, 7: normal operation 
       (Units 2 to 4: outage due to regular inspection)
[Thermal Power Station] 
- Hirono Thermal Power Station Unit 2 and 4: Shutdown due to the earthquake
[Hydro Power Station] 
- Power supply has returned to normal and facilities damaged by the 
  earthquake are now being handled in a timely manner.
[Impacts on Transmission Facilities] 
- Power supply has returned to normal and facilities damaged by the 
  earthquake are now being handled in a timely manner.
[Perspective of Power Supply and Demand Balance in this Summer]  
We have worked to restore electricity supply after our nuclear and thermal 
power facilities were severely damaged by Tohoku-Chihou-Taiheiyou-Oki 
Earthquake. This time, we revised that the supply capacity in this summer 
would increase because we could plan to secure an additional capacity. 
However, in order to maintain the policy of avoiding further implementation 
of rolling blackouts during the summer, in addition to the above increase 
of the supply capacity, we sincerely ask for your continued cooperation in 
reducing electricity consumption. Now we are creating concrete measures 
considering "Outline of Countermeasures for Power Supply and Demand During 
Summertime" presented by the Electricity Supply-Demand Emergency Response 
Headquarters of the Japanese government. 
                                                    (Previously Announced)

It is expected that we will be able to maintain the policy of avoiding 
further implementation of planned blackouts this June because it is 
estimated that we will be able to secure the capacity exceeding the maximum 
forecasted demand as of now, thanks to your understanding as well as 
cooperation on saving electricity.

However, in the event that an unplanned outage such as excessive continuous 
operation in old plants and a sudden increase of power demand due to 
unusual hot temperature occur, there is a possibility to affect a stable 
power supply. In order to maintain the policy of avoiding planned blackouts, 
we will steadily implement installation of additional power capacity as we 
have planned, and we continuously do our best efforts to secure supply 
capacity. We apologize for the inconvenience this may cause and appreciate 
for your cooperation to save electricity. 
Appendix: Past Progress (PDF 187KB) 

* Revised past progress 
back to page top


to TOP