Due to the Tohoku-Chihou-Taiheiyou-Oki Earthquake which occurred on March
11, 2011, TEPCO's facilities including our nuclear power stations have been
severely damaged. We deeply apologize for the anxiety and inconvenience
caused.
With regard to the accident at Fukushima Daiichi Nuclear Power Station, on
April 17, we have compiled the roadmap towards restoration from the accident
and then we updated the roadmap considering the current situation, on June 17.
By bringing the reactors and spent fuel pools to a stable cooling condition
and mitigating the release of radioactive materials, we will make every
effort to enable evacuees to return to their homes and for all citizens to
be able to secure a sound life.
Below is the status of TEPCO's major facilities.
*Updates from previous press release are underlined.
[Nuclear Power Station] Fukushima Daiichi Nuclear Power Station:
Units 1 to 3: shutdown due to the earthquake
(Units 4 to 6: outage due to regular inspections)
- At 11:48 am on June 19th, we stopped the equipment to supply nitrogen to
the primary containment vessel of Unit 1 due to switching the power in
the site. At 4:15 pm on the same day, we resumed its operation.
- At 11:03 am on June 19, we stopped the operation of fuel pool cooling and
filtering system. At 4:00 pm on the same day we resumed its operation.
- At 12:12 pm on June 19th, we stopped local exhausters in the primary
containment vessel of Unit 2 due to switching the power in the site. At
4:22 pm on the same day we resumed their operation.
- At 8:51 pm on June 19 we began to open the air lock, while coordinating
a degree of its opening. Then we confirmed a result of monitoring dose
rate in the air and evaluated there was no impact in the surrounding area.
At 5:00 am on June 20 we fully opened the air lock.
- At 1:31 pm on June 18 we started transferring water accumulated in the
basement of the turbine building of Unit 3 to Centralized Radiation Waste
Treatment Facility (Miscellaneous Solid Waste Volume Reduction Treatment
Building). At 12:02 am on June 20, the transfer was finished.
- On 7: 30 pm on June 19 we conducted a water flow test using highly
concentrated contaminated water in Cesium adsorption Instruments of the
water treatment facility and finished it at 11:45 pm on the same day.
- On June 19th, workers sprayed dust inhibitors to approximately 6,810 m2
of area at the west side of the reactor building of Unit 2.
Fukushima Daini Nuclear Power Station:
Units 1 to 4: shutdown due to the earthquake
Kashiwazaki Kariwa Nuclear Power Station:
Units 1, 5, 6, 7: normal operation
(Units 2 to 4: outage due to regular inspection)
[Thermal Power Station]
- Hirono Thermal Power Station Unit 2 and 4: Shutdown due to the earthquake
[Hydro Power Station]
- Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Impacts on Transmission Facilities]
- Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Perspective of Power Supply and Demand Balance in this Summer]
We have worked to restore electricity supply after our nuclear and thermal
power facilities were severely damaged by Tohoku-Chihou-Taiheiyou-Oki
Earthquake. This time, we revised that the supply capacity in this summer
would increase because we could plan to secure an additional capacity.
However, in order to maintain the policy of avoiding further implementation
of rolling blackouts during the summer, in addition to the above increase
of the supply capacity, we sincerely ask for your continued cooperation in
reducing electricity consumption. Now we are creating concrete measures
considering "Outline of Countermeasures for Power Supply and Demand During
Summertime" presented by the Electricity Supply-Demand Emergency Response
Headquarters of the Japanese government.
(Previously Announced)
It is expected that we will be able to maintain the policy of avoiding
further implementation of planned blackouts this June because it is
estimated that we will be able to secure the capacity exceeding the maximum
forecasted demand as of now, thanks to your understanding as well as
cooperation on saving electricity.
However In the event that an unplanned outage such as excessive continuous
operation in old plants and a sudden increase of power demand due to
unusual hot temperature occur, there is a possibility to affect a stable
power supply. In order to maintain the policy of avoiding rolling blackouts,
we steadily implement to install additional power capacity we have planed,
and we continuously do our best efforts to secure supply capacity. We
apologize for the inconvenience this may cause and appreciate for your
cooperation to save electricity.
Appendix: Past Progress (PDF 173KB)
* Revised past progress